Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Produce drawings to enable road construction
Produce drawings to enable road construction
Module
National Code
VU23936
VU23936
State Code
BB725
BB725
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
18/09/2026
Field of Education
030901 - Construction Engineering
Nominal Hours
60
Description
This unit describes the performance outcomes, knowledge and skills required to complete typical road drawings required in the construction of urban and rural roads to comply with the relevant drawing presentation guidelines.
It requires the ability to interpret and plot from survey data, plot horizontal alignment, tabulate and plot longitudinal section and cross section information and draw required intersections utilising computer aided drawing (CAD) software.
The unit applies to a person working at paraprofessional level in a civil engineering environment where drawings of roads are prepared.
No licensing, legislative, regulatory or certification requirements apply to this unit at the time of accreditation.
It requires the ability to interpret and plot from survey data, plot horizontal alignment, tabulate and plot longitudinal section and cross section information and draw required intersections utilising computer aided drawing (CAD) software.
The unit applies to a person working at paraprofessional level in a civil engineering environment where drawings of roads are prepared.
No licensing, legislative, regulatory or certification requirements apply to this unit at the time of accreditation.
General notes
No information
No information
Elements and Performance Criteria
Identify road project to be drawn
- 1.1 Established occupational health and safety/workplace health and safety (OHS/WHS) requirements and risk control measures and procedures are followed in the work area
- 1.2 Existing drawings, relevant documentation, work specifications are sought and discussed with appropriate personnel
- 1.3 Appropriate personnel are consulted to ensure the work is co-ordinated effectively with others involved at the workplace
Plan drafting approach
- 2.1 Work specifications and related documentation required for the drawing project is collected and analysed
- 2.2 Resources and equipment needed for the work are obtained and set up in accordance with enterprise procedures and checked for correct operation
Complete the drawings
- 3.1 Drafting references and equipment are used according to enterprise procedures
- 3.2 Earthworks volumes are calculated and a mass haul diagram is plotted
- 3.3 Survey data is interpreted and plotted
- 3.4 Horizontal alignment, and longitudinal section information is tabulated and plotted
- 3.5 Cross section information is tabulated and plotted
- 3.6 Using existing plans, sections and collated details Intersections drawings are prepared
- 3.7 Quality assurance checks are carried out in accordance with the checking plan
- 3.8 Drawings are completed to comply with the relevant drawing presentation guidelines and enterprise procedures
- 3.9 Decisions for dealing with unexpected situations are made from discussions with appropriate personnel, job specifications and enterprise procedures
- 3.10 Drawings are reviewed with appropriate personnel and against work specifications and amended as required
Present and archive final drawings
- 4.1 File naming conventions, storage and back up processes are followed in accordance with enterprise procedure
- 4.2 Drawings are outputted to printer/plotters or issued as PDF files
- 4.3 Final drawings are presented and discussed with appropriate personnel in accordance with enterprise procedures