Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Plan renewable energy (RE) projects
Plan renewable energy (RE) projects
Unit of competency
National Code
UEERE0044
UEERE0044
State Code
OCB55
OCB55
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
12/07/2021
Field of Education
080315 - Project Management
Original Release Date
12/07/2021
Nominal Hours
54
Description
This unit involves the skills and knowledge required to plan a renewable energy (RE) project.It includes preparing to plan a project, developing a RE project plan proposal and obtaining approval for a project plan.No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Prepare to plan project
- 1.1 Work health and safety (WHS)/occupational health and safety (OHS) processes and procedures for relevant work area are identified, interpreted and applied in accordance with workplace procedures
- 1.2 Relevant techniques for project planning are reviewed and applied in accordance with workplace policies
- 1.3 Scope of the project is determined from design brief specification and/or other relevant documentation and discussions with relevant person/s
2 Develop RE project plan proposal
- 2.1 Estimated plant, material, labour and other costs are obtained from relevant person/s in accordance with workplace policies and procedures
- 2.2 Project budget is established from estimated plant, material, labour and other costs in accordance with workplace policies and procedures
- 2.3 Critical path analysis is applied to developing workflow strategies
- 2.4 Sources and availability of materials and human resources for the project are identified in accordance with workplace policies and procedures
- 2.5 Risk management strategies are identified, obtained and applied in the project plan
- 2.6 Project plan is reviewed against all inputs and adjusted to rectify any anomalies
- 2.7 Project plan proposal is documented in accordance with workplace policies and procedures
3 Obtain approval for project plan
- 3.1 Project plan is presented and discussed with relevant person/s
- 3.2 Alterations to the project plan resulting from the presentation/discussion are negotiated with relevant person/s within constraints of workplace policies
- 3.3 Final project plan is documented and approval obtained from relevant person/s
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| WC693 | UEENEEK122A | Plan renewable energy (RE) projects | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| OEU05 | UEERE0085 | Plan renewable energy (RE) projects | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BFM3 | UEE62020 | Advanced Diploma of Engineering Technology - Renewable Energy | Qualification |
| BFJ7 | UEE60920 | Advanced Diploma of Renewable Energy Engineering | Qualification |