Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Undertake complex environmental project work

Undertake complex environmental project work

Unit of competency
National Code
MSS027018
State Code
OAF51
TGA Status
Deleted
DTWD Status
Deleted
Current Release Number
1.00
Current Release Date
22/10/2018
State Implementation and Classification
Approved Date
19/02/2019
Field of Education
080315 - Project Management
Original Release Date
19/02/2019
Nominal Hours
120
Description
This unit describes the skills and knowledge to carry out complex environmental project activities and/or coordinate the activities of concurrent projects. Personnel are required to review and confirm the requirements of each project activity, organise and carry out project activities, oversee the progress of projects activities and finalise the work in each case. They may be responsible for all or some project deliverables, work in teams on aspects of projects, and may liaise with multiple clients. This unit applies to environmental site coordinators, environmental managers and senior environmental officers working in all industry sectors. They may also work under the supervision of an environmental scientist or engineer, site manager or workplace environmental manager.No licensing or certification requirements exist at the time of publication. Relevant legislation, industry standards and codes of practice within Australia must be applied.
Notes
Elements and Performance Criteria
1 Review and confirm project requirements with manager
  • 1.1 Confirm own role, limits of responsibility and reporting requirements for assigned projects
  • 1.2 Read and interpret workplace project management procedures and controls
  • 1.3 Read and interpret background information for each project to clarify intended outcomes, key stakeholders, drivers and likely constraints
  • 1.4 Read and interpret project plans and clarify roles and responsibilities of project team members, deliverables, timeframes, stakeholder involvement and available resources
  • 1.5 Negotiate changes to project plans in accordance with workplace project management procedures
  • 1.6 Update project plans with confirmed information for milestones, resources, team members and stakeholder details
2 Organise and undertake project activities
  • 2.1 Use project management tools to achieve efficient integration and sequencing of projects activities
  • 2.2 Consolidate schedules of activities, timeframes and milestones on a single planning management framework to enable efficient monitoring of each project activity
  • 2.3 Identify possible and actual clashes in activities and negotiate alternatives with management
  • 2.4 Carry out own project tasks in accordance with project plans and manage any variations in accordance with workplace project management procedures
  • 2.5 Capture, record and store required project information and data
  • 2.6 Support project team members to achieve project milestones and assigned outputs with resources available
  • 2.7 Seek manager’s advice when challenges are beyond own technical competence or when input from environmental specialists is required
3 Manage the progress of multiple projects
  • 3.1 Anticipate risks to progress or achievement of project outcomes and notify relevant personnel in accordance with risk management plans
  • 3.2 Monitor completion of project activities and progress against targets and milestones
  • 3.3 Negotiate and implement corrective actions with project team members and managers in accordance with workplace project management procedures and controls
  • 3.4 Develop solutions in response to project problems and unforeseen or changed circumstances in consultation with manager
  • 3.5 Provide regular project reports in accordance with project plans and workplace project management procedures
4 Finalise project activities
  • 4.1 Provide deliverables for each project activity in accordance with the specified timeframe and quality standards
  • 4.2 Provide deliverables for each project activity in accordance with the specified timeframe and quality standards
  • 4.3 Ensure all project records are accurate and complete
  • 4.4 Evaluate project processes to identify unresolved issues and recommend opportunities for improvement of future project activities
  • 4.5 Write timely and accurate project reports in accordance with workplace project management procedures and using the specified style, language and formats
  • 4.6 Archive project information and return borrowed and unused resources in accordance with workplace project management procedures