Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Provide validation and assurance of costs

Provide validation and assurance of costs

Unit of competency
National Code
DEFFIN029
State Code
BBC10
TGA Status
Current
DTWD Status
Approved
Current Release Number
1.00
Current Release Date
17/08/2017
State Implementation and Classification
Approved Date
21/02/2018
Field of Education
080317 - Quality Management
Original Release Date
21/02/2018
Nominal Hours
0
Description
This unit describes the skills required to provide assurance of cost estimates for Defence projects and programs.This unit applies to those working in the public sector Finance Domain who would be required to undertake cost assurance activities related as part of their duties.The skills and knowledge described in this unit must be applied within the legislative, regulatory and policy environment in which they are carried out. Organisational policies and procedures must be consulted and adhered to, particularly those related to cost estimation activities.Those undertaking this unit would be working under minimal supervision and/or supervising small teams while undertaking financial management tasks. They would perform complex tasks in familiar context.No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Determine that the estimate is well documented
  • 1.1 Check that cost estimation documentation identifies data sources and justifies any assumptions
  • 1.2 Review the documented method used to develop cost estimate and determine whether estimate can be replicated or updated
  • 1.3 Check that schedule milestones and deliverables are documented and consistent with the cost estimation
2 Determine that the estimate is comprehensive
  • 2.1 Confirm that the cost estimate is complete and accounts for all possible costs, including indirect costs
  • 2.2 Review estimate to determine that no cost elements have been omitted or repeated
3 Determine that the estimate is accurate
  • 3.1 Confirm that estimates are based on the most likely costs
  • 3.2 Review estimates for errors
  • 3.3 Check that appropriate escalations factors have been used
  • 3.4 Review and validate the estimating technique used for each cost element
4 Determine that the estimate is credible
  • 4.1 Test key cost estimations for sensitivity
  • 4.2 Perform a risk and uncertainty analysis to determine the level of risk associated with the estimate
  • 4.3 Cross check the estimate against an independent estimate to determine whether other estimation methods produce similar results
No information