Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Develop the application of enterprise systems in manufacturing

Develop the application of enterprise systems in manufacturing

Unit of competency
National Code
MSACMT660A
State Code
W9025
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
01/12/2005
State Implementation and Classification
Approved Date
30/06/2011
Field of Education
080301 - Business Management
Original Release Date
30/06/2011
Nominal Hours
60
Description
This unit covers the knowledge and skills needed to continuously modify and improve or develop new enterprise wide systems such as SCADA, ERP, MRPII and similar. Typically the development of such a system will be in liaison with an appropriate technical expert who may be an internal expert or an external consultant.
Notes
Elements and Performance Criteria
1. Monitor information and control needs of organisation
  • 1.1. Check the use of current information1.2. Check the operation of current control systems1.3. Communicate regularly with key information users regarding improved/changed information/control needs1.4. Identify short comings in information/control provision1.5. Take appropriate action on information/control needs to meet organisational needs
2. Check the current system against organisation needs
  • 2.1. Check the routine use of the system2.2. Communicate regularly with key stakeholders about current system use and application2.3. Identify problems/issues2.4. Take appropriate action on problems/issues
3. Determine developments needed in a new or significantly modified system
  • 3.1. Identify needs requiring a new system or development of modifications to the current system3.2. Draft scope, specifications and outcomes required3.3. Liaise with key stakeholders and relevant technical experts to refine scope, specifications and outcomes needed in new or modified system3.4. Agree final scope, specifications and outcomes
4. Develop system
  • 4.1. Develop project plan4.2. Ensure ongoing consultation with all relevant stakeholders4.3. Manage development project4.4. Manage trialling of modified system4.5. Ensure modified system meets organisational requirements
5. Implement modified system
  • 5.1. Liaise with all affected personnel5.2. Develop and agree an implementation strategy5.3. Ensure all personnel have required skills5.4. Implement modified system5.5. Monitor implementation and modify as required

System Control and Data Acquisition (SCADA) is a general term applied to a number of systems which automatically collect critical process data, perform required mathematical manipulations on it and then make control decisions and/or give required information personnel for action.

In the continuous manufacturing sector, the SCADA system is sometimes integrated into other sophisticated computer control systems such as Distributed Control System (DCS) and indeed these systems do merge in advanced systems. These organisations may simply refer to their SCADA as the DCS or other similar term (such as the proprietary name of the computer system).


Planning software is a general term applied to a number of software systems which integrate a range of business information such as finance, logistics maintenance and production. It is frequently referred to by names such as ERP, SAP, MRP/MRPII.


Competitive manufacturing organisations encompass the entire production system, beginning with the customer, and includes the product sales outlet, the final assembler, product design, raw material mining and processing and all tiers of the value chain (sometimes called the supply chain). Any truly 'competitive' system is highly dependent on the demands of its customers and the reliability of its suppliers. No implementation of competitive manufacturing can reach its full potential without including the entire 'enterprise' in its planning.

Overview of assessment requirements
The person will be able to modify an existing system to accommodate changed needs of the organisation, or make improvements to an existing system to better do what it is already doing. They could also work with relevant experts to implement a new system to an organisation, process or part of a process.

What are the specific resource requirements for this unit?
Access to an organisation operating systems and undertaking developments to its system.

In what context should assessment occur?
Assessment would need to occur in an organisation using or introducing SCADA, resource planning or similar systems or a suitable simulation.

Are there any other units which could or should be assessed with this unit or which relate directly to this unit?
This unit could be assessed concurrently with units of project management, product design or process improvement/ optimisation.

What method of assessment should apply?
Assessors must be satisfied that the person can consistently perform the unit as a whole, as defined by the Elements, Performance Criteria, skills and knowledge. A holistic approach should be taken to the assessment.
Assessors should gather sufficient, fair, valid, reliable, authentic and current evidence from a range of sources. Sources of evidence may include direct observation, reports from supervisors, peers and colleagues, project work, samples, organisation records and questioning. Assessment should not require language, literacy or numeracy skills beyond those required for the unit.
The assessee will have access to all techniques, procedures, information, resources and aids which would normally be available in the workplace.
The method of assessment should be discussed and agreed with the assessee prior to the commencement of the assessment.

What evidence is required for demonstration of consistent performance?
Where evidence is provide from small developments, a range of development activities should be considered to provide sufficient evidence. Where evidence is from one complex development project, this may provide sufficient evidence.

Replaced By
State Code National Code Title Type
WD571 MSS405060A Develop the application of enterprise control systems in an organisation Unit of competency
State Code National Code Title Type
W529 MSA61108 Advanced Diploma of Competitive Manufacturing Qualification