Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Undertake interior finishing of swimming pools and spas

Undertake interior finishing of swimming pools and spas

Unit of competency
National Code
CPCSPS4009
State Code
OCM12
TGA Status
Current
DTWD Status
Approved
Current Release Number
1.00
Current Release Date
27/11/2020
State Implementation and Classification
Approved Date
01/06/2021
Field of Education
040399 - Building, N.e.c.
Original Release Date
01/06/2021
Nominal Hours
30
Description
This unit specifies the skills and knowledge required to undertake interior finishes to variously shaped swimming pools and spas. It includes applying interior finishes to concrete and fibreglass swimming pools and spas.This unit reflects the role of those who are responsible for the application of interior finish to swimming pools and spas. It applies in a range of contexts:private swimming poolspublic swimming pools, including:hydrotherapy and therapeutic exercise poolswading and receiving pools associated with water slideswave pools.This unit is suitable for those using specialised knowledge to complete routine and non-routine tasks, and their own judgement to deal with predictable and sometimes unpredictable problems.No licensing or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Plan interior finishing of swimming pool and spa.
  • 1.1 Access, read and interpret relevant swimming pool and spa information from plans, specifications, codes and standards.
  • 1.2 Interpret and apply work health and safety and environmental requirements.
  • 1.3 Identify properties of materials and requirements for application and installation for internal finish of the project.
  • 1.4 Calculate material quantities required as specified.
  • 1.5 Determine project timeframes, job priorities and sequence of job tasks in consultation with others on site.
  • 1.6 Schedule delivery of material and components and required plant and equipment.
2 Prepare for the finishing work.
  • 2.1 Confirm materials match the delivery docket and comply with job specifications.
  • 2.2 Select, fit and use personal protective equipment appropriate for activity.
  • 2.3 Check plant and equipment for serviceability.
  • 2.4 Drain excess water from swimming pool and spa.
  • 2.5 Protect lighting and recirculation system components against damage from subsequent works.
3 Finish pool and spa interior.
  • 3.1 Repair damage to or imperfections in swimming pool and spa surface.
  • 3.2 Use appropriate techniques to wash, seal and bond surface.
  • 3.3 Protect and maintain pool shell to avoid premature drying of pool finish.
  • 3.4 Establish a starting point for application of interior finish and ensure correct process and sequence are followed.
  • 3.5 Check application techniques for consistent thickness, colour, shape and smoothness.
  • 3.6 Confirm interior finish is completed to specifications and to manufacturer guidelines.
4 Clean up site.
  • 4.1 materials in accordance with workplace and environmental requirements.
  • 4.2 Clean tools and equipment, check for serviceability, report any damage or faults and store and secure.
No information
No information
No information
State Code National Code Title Type
BGC9 CPC40820 Certificate IV in Swimming Pool and Spa Building Qualification