Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Carry out lifting using multiple cranes
Carry out lifting using multiple cranes
Unit of competency
National Code
RIIHAN306A
RIIHAN306A
State Code
WB282
WB282
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
17/09/2012
Field of Education
030717 - Plant And Machine Operations
Original Release Date
17/09/2012
Nominal Hours
40
Description
This unit covers carrying out lifting using multiple cranes in the resources and infrastructure industries. It includes planning and preparing for a multiple lift and carrying out a multiple lift. Licensing, legislative, regulatory and certification requirements that apply to this unit can vary between states, territories, and industry sectors. Relevant information must be sourced prior to application of the unit.
Notes
Elements and Performance Criteria
1. Plan and prepare for multiple lift
- 1.1. Access, interpret and apply compliance documentation relevant to the work activity
- 1.2. Obtain, interpret and clarify/confirm work requirements in the form of shift briefings, handover details or work orders before proceeding
- 1.3. Conduct work preparation in accordance with AS2550, legislation and manufacturers/site requirements
- 1.4. Carry out assembly and dismantling of boom/jib
- 1.5. Resolve coordination activities with others at the site prior to commencement of, and during, the work activity
- 1.6. Carry out crane pre-start, start-up, park-up and shutdown procedures
- 1.7. Position, stabilise and level cranes prior to commencement of multiple lift in accordance with relevant standards and specifications, and approved man-basket permit and use procedures
2. Carry out multiple lift
- 2.1. Obtain approval to carry out a multiple crane lift from the appropriate statutory authority
- 2.2. Plan multiple lift and obtain approval for lifting plan by an authorised person
- 2.3. Clarify and confirm multiple lift activities and responsibilities with the other crane operators
- 2.4. Carry out the multiple lift under the supervision of an authorised person in accordance with the appropriate standards, regulations and site safety requirements
- 2.5. Prepare load for lift in accordance with crane limitations and rigging requirements
- 2.6. Confirm the work area is clear and safe prior to commencing multiple lift
- 2.7. Interpret signals in accordance with AS2550
- 2.8. Use relevant crane controls and functions within manufacturer's specifications to effectively lift and position loads
- 2.9. Act on or report monitoring systems and alarms
- 2.10. Recognise and respond to hazardous and emergency situations
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Compliance documentation may include:
legislative, organisation and site requirements and procedures
manufacturer's guidelines and specifications
Australian standards, including:
AS2550
cranes and state-based legislation and regulations
safety information and procedures
management plans
OHS policy
code of practice
manufacturer's instructions
safe working or job procedures
Employment and workplace relations legislation
Equal Employment Opportunity and Disability Discrimination legislation
Shift briefings/handover details/work orders may include:
crane equipment to be used
nature and scope of tasks
details of load chart/factors
achievement targets
working conditions
site lighting arrangements
defects on equipment
hazards and potential hazards
coordination requirements/issues
Work preparation may include:
selection of stable base
clarification of multiple lift procedure
avoidance of obstacles and hazards
identification of loads
identification and selection of lifting equipment
inspection and certification of lifting equipment
fitting of optional implements/accessories
management of permits and tags
Plan multiple lifts may include:
an assessment of the load to be carried by each crane
determination of the types of cranes suitable for use
the safety margins and hazard control measures to be used in the lift
the sequence of operations
Site safety requirements may include:
control and safety of slewing speed
selection and observance of safe working levels and angles
avoidance of obstacles and hazards
boarding and disembarking procedures
observation of wind restrictions
communications and signalling procedures
Crane controls and functions may include:
boom up
boom down
boom extensions
hoist up
hoist down
manual jib and fly-jib extensions
slew
Hazardous and emergency situations may include:
accidents
injuries
power lines
trees
overhead service lines
bridges
surrounding buildings
obstructions
structures
facilities
other equipment
dangerous materials
earthworks
underground services
adverse weather conditions
time of day
Compliance documentation may include:
legislative, organisation and site requirements and procedures
manufacturer's guidelines and specifications
Australian standards, including:
AS2550
cranes and state-based legislation and regulations
safety information and procedures
management plans
OHS policy
code of practice
manufacturer's instructions
safe working or job procedures
Employment and workplace relations legislation
Equal Employment Opportunity and Disability Discrimination legislation
Shift briefings/handover details/work orders may include:
crane equipment to be used
nature and scope of tasks
details of load chart/factors
achievement targets
working conditions
site lighting arrangements
defects on equipment
hazards and potential hazards
coordination requirements/issues
Work preparation may include:
selection of stable base
clarification of multiple lift procedure
avoidance of obstacles and hazards
identification of loads
identification and selection of lifting equipment
inspection and certification of lifting equipment
fitting of optional implements/accessories
management of permits and tags
Plan multiple lifts may include:
an assessment of the load to be carried by each crane
determination of the types of cranes suitable for use
the safety margins and hazard control measures to be used in the lift
the sequence of operations
Site safety requirements may include:
control and safety of slewing speed
selection and observance of safe working levels and angles
avoidance of obstacles and hazards
boarding and disembarking procedures
observation of wind restrictions
communications and signalling procedures
Crane controls and functions may include:
boom up
boom down
boom extensions
hoist up
hoist down
manual jib and fly-jib extensions
slew
Hazardous and emergency situations may include:
accidents
injuries
power lines
trees
overhead service lines
bridges
surrounding buildings
obstructions
structures
facilities
other equipment
dangerous materials
earthworks
underground services
adverse weather conditions
time of day
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:
knowledge of the requirements, procedures and instructions for carrying out lifting using multiple cranes
implementation of requirements, procedures and techniques for the safe, effective and efficient completion of lifting using multiple cranes
working with others to undertake and carrying out lifting using multiple cranes that meet all of the required outcomes
consistent, timely completion of carrying out lifting using multiple cranes that safely, effectively and efficiently meet the required outcomes
Context of and specific resources for assessment
This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.
Assessment of this competency requires typical resources normally used in a resources and infrastructure sector environment. Selection and use of resources for particular worksites may differ due to the site circumstances.
The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.
Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.
Aboriginal people and other people from a non English speaking background may have second language issues.
Where applicable, physical resources should include equipment modified for people with disabilities. Access must be provided to appropriate learning and/or assessment support when required.
Method of assessment
This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:
written and/or oral assessment of the candidate's required knowledge
observed, documented and/or first hand testimonial evidence of the candidate's:
implementation of appropriate requirements, procedures and techniques for the safe, effective and efficient achievement of required outcomes
consistent achievement of required outcomes
first hand testimonial evidence of the candidate's:
working with others to undertake and complete carrying out lifting using multiple cranes
Guidance information for assessment
Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:
knowledge of the requirements, procedures and instructions for carrying out lifting using multiple cranes
implementation of requirements, procedures and techniques for the safe, effective and efficient completion of lifting using multiple cranes
working with others to undertake and carrying out lifting using multiple cranes that meet all of the required outcomes
consistent, timely completion of carrying out lifting using multiple cranes that safely, effectively and efficiently meet the required outcomes
Context of and specific resources for assessment
This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.
Assessment of this competency requires typical resources normally used in a resources and infrastructure sector environment. Selection and use of resources for particular worksites may differ due to the site circumstances.
The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.
Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.
Aboriginal people and other people from a non English speaking background may have second language issues.
Where applicable, physical resources should include equipment modified for people with disabilities. Access must be provided to appropriate learning and/or assessment support when required.
Method of assessment
This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:
written and/or oral assessment of the candidate's required knowledge
observed, documented and/or first hand testimonial evidence of the candidate's:
implementation of appropriate requirements, procedures and techniques for the safe, effective and efficient achievement of required outcomes
consistent achievement of required outcomes
first hand testimonial evidence of the candidate's:
working with others to undertake and complete carrying out lifting using multiple cranes
Guidance information for assessment
Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| W2295 | MNMG339A | Carry out lifts using multiple cranes | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| WH312 | RIIHAN306D | Carry out lifting using multiple cranes | Unit of competency |