Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Implement a track work authority and manage rail traffic through worksites
Implement a track work authority and manage rail traffic through worksites
Unit of competency
National Code
TLIL3083
TLIL3083
State Code
AVI68
AVI68
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
23/02/2016
Field of Education
039907 - Rail Operations
Original Release Date
23/02/2016
Nominal Hours
15
Description
This unit describes the skills and knowledge required to implement a track work authority (TWA) and manage rail traffic through worksites in accordance with Rail Infrastructure Manager system of safeworking, rules, procedures and protocols for rail safety. It includes preparing for a TWA, managing rail traffic, fulfilling a TWA and managing unsafe situations or emergencies.People achieving competence in this unit will need to fulfil the applicable state/territory legislated rail safety requirements and to comply with relevant codes of practice and/or guidelines.The unit includes the application of Rail Infrastructure Manager systems of safeworking, rules, procedures and protocols for rail safety but does not include the implementation of worksite protection. No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Prepare for track work authority
- 1.1 Worksite protection plan is sourced and TWA terms are read and clarified, as required
- 1.2 Hazards are identified, risks are assessed and control measures implemented
- 1.3 Network control officer is notified of the intention to use a TWA
- 1.4 Protection officer worksite protection responsibilities are identified from worksite protection plan
2 Issue a track work authority
- 2.1 Permission to issue a TWA is requested from network control officer
- 2.2 Permission to use a TWA is documented in accordance with Rail Infrastructure Manager requirements
- 2.3 Equipment required for TWA protection is identified and checked for functional condition
- 2.4 Protection is placed in accordance with worksite protection plan
- 2.5 Work group supervisor is advised that protection is in place
3 Manage rail traffic
- 3.1 Vigilance is maintained and protection officer is alerted to approaching rail traffic in accordance with workplace rules and procedures
- 3.2 Arrangements are made for equipment to be removed from the danger zone
- 3.3 Work group is instructed to move to a safe place prior to passage of rail traffic
- 3.4 Safety of track for passage of rail traffic is confirmed with work group supervisor
- 3.5 Instructions are issued to rail traffic in accordance with workplace procedures
- 3.6 Worksite protection is implemented prior to work groups entering the track worksite in accordance with workplace rules and procedures
- 3.7 Protection, placement and equipment is continually monitored for effectiveness in accordance with safety assessment
4 Fulfil a track work authority
- 4.1 Communication is conducted with work group supervisor to confirm that work activity is complete and track is safe
- 4.2 Network control officer is advised that the TWA has been fulfilled
- 4.3 Fulfilment of TWA is documented in accordance with Rail Infrastructure Manager and/or organisational requirements
5 Manage unsafe situations or emergencies
- 5.1 Unsafe situations and/or emergencies are identified
- 5.2 Work group is instructed to move to a safe place
- 5.3 Appropriate action is taken to minimise risk and/or injury in accordance with workplace procedures
- 5.4 Emergencies and/or incidents are recorded and reported to relevant personnel in accordance with workplace procedures
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| WG231 | TLIL3083A | Implement a track work authority and manage rail traffic through worksites | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| AD266 | TLISS00107 | Control Rail Traffic Through Worksite Skill Set | Skill set |
| BHI0 | TLI32721 | Certificate III in Track Protection | Qualification |
| AWQ0 | TLI32715 | Certificate III in Track Protection | Qualification |