Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Plan monument construction

Plan monument construction

Unit of competency
National Code
CPCCST3011
State Code
OCP46
TGA Status
Current
DTWD Status
Approved
Current Release Number
2.00
Current Release Date
24/12/2024
State Implementation and Classification
Approved Date
01/06/2021
Field of Education
040309 - Bricklaying And Stonemasonry
Original Release Date
01/06/2021
Nominal Hours
10
Description
This unit specifies the skills and knowledge required to prepare plans and specifications for the construction phase of monuments in cemeteries. It includes identifying and meeting customer needs and state and local legislative requirements. This unit applies to stonemasons who work independently, in a team or under supervision to plan monument construction relating to stonemasonry work in a workshop setting, on a new or existing structure.A person working at this level would be expected to take responsibility for organising and completing tasks assigned to them without needing close supervision.Completion of the general construction induction training program specified by the model Code of Practice for Construction Work is required for any person who is to carry out construction work. Achievement of CPCWHS1001Prepare to work safely in the construction industrymeets this requirement. No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Identify design and legislative requirements.
  • 1.1 Read, interpret and apply relevant information, government legislation, standards and codes appropriate to monument construction in cemeteries.
  • 1.2 Follow relevant information from workplace procedures, workplace safety and environmental documentation.
  • 1.3 Determine monument design and materials with customer.
  • 1.4 Check selected materials conform to proposed design.
  • 1.5 Select and check drawing equipment is sufficient for job design.
2 Prepare plans.
  • 2.1 Determine job priorities, time frames and sequence job tasks in consultation with others.
  • 2.2 Design foundation details according to soil type and monument size.
  • 2.3 Design monument to meet the client’s requirements.
  • 2.4 Check design with client for approval.
3 Finalise design and specifications for submission.
  • 3.1 Complete drawings applying drafting conventions and detailing joining, supporting and reinforcing requirements.
  • 3.2 Compile specifications ensuring direct relationship with drawings and regulations.
  • 3.3 Check drawing and specifications and edit for consistency.
  • 3.4 Print drawings and specifications in preparation for distribution.
No information
No information
Replaces
State Code National Code Title Type
W9566 CPCCST3011A Plan monument construction Unit of competency
State Code National Code Title Type
BGE7 CPC32320 Certificate III in Stonemasonry Qualification