Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Perform switching to a switching program

Perform switching to a switching program

Unit of competency
National Code
UEPOPS124
State Code
ODY58
TGA Status
Current
DTWD Status
Approved
Current Release Number
1.00
Current Release Date
20/04/2022
State Implementation and Classification
Approved Date
14/04/2023
Field of Education
031301 - Electrical Engineering
Original Release Date
14/04/2023
Nominal Hours
27
Description
This unit involves the skills and knowledge required to perform switching to a switching program.An electricalswitchcan alternate a load between two sources either manually or automatically when sensors detect one of the sources has lost or gained power. A switchis installed where the backup generator is located so that the generator can be used to provide temporary electrical power, as required.Competency in this unit requires the ability to prepare for switching program, carry out switching program, and complete all documentation. Individuals will, in general, work as an operator in, in a power generation facility.Power generation plant operators are trained and authorised to isolate, prepare plant and issue permits to work.No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Prepare for switching program
  • 1.1 Authorisation is confirmed to perform switching operation with coordinating personnel in accordance with workplace procedures
  • 1.2 Work health and safety (WHS)/occupational health and safety (OHS) regulations, legislative requirements, codes of practice, manufacturers’ recommendations and specifications, environmental requirements and workplace procedures are identified, applied and monitored
  • 1.3 Contingency plan is discussed with personnel coordinating switching program in accordance with workplace procedures
  • 1.4 Permits and access requirements are identified prior to program commencement in accordance with workplace procedures
  • 1.5 Documentation is received and checked prior to starting switching program in accordance with workplace procedures
2 Carry out switching program
  • 2.1 Personnel involved in switching program are confirmed and directed to switching locations in accordance with workplace procedures
  • 2.2 Communication is established and maintained with personnel coordinating switching program in accordance with workplace procedures
  • 2.3 Access to electrical power generation plant is obtained in accordance with workplace procedures
  • 2.4 Switching program steps are verified before and after each operation in accordance with workplace procedures
  • 2.5 Switching steps are documented on completion of each operation in accordance with workplace procedures
  • 2.6 Permits are issued, monitored and recorded in accordance with workplace procedures
  • 2.7 Switching program is completed and outcomes recorded in accordance with workplace procedures
3 Complete documentation
  • 3.1 Equipment problems, abnormalities and status are reported in accordance with workplace
  • 3.2 Documentation is updated in accordance with workplace procedures