Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Saw and cut concrete pavements to initiate planned cracks
Saw and cut concrete pavements to initiate planned cracks
Unit of competency
National Code
RIICRC319
RIICRC319
State Code
WC338
WC338
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
16/08/2012
Field of Education
030901 - Construction Engineering
Original Release Date
16/08/2012
Nominal Hours
16
Description
This unit covers the cutting of concrete to initiate planned cracks in road pavement operations in the civil construction industry. It includes the conduct of planning and preparing, selecting and operating a concrete saw and cleaning up. Licensing, legislative, regulatory and certification requirements that apply to this unit can vary between states, territories and industry sectors. Relevant information must be sourced prior to application of the unit.
Notes
Elements and Performance Criteria
1. Plan and prepare for operations
- 1.1 Access, interpret and apply compliance documentation relevant to the use of hand and power tools
- 1.2 Obtain, confirm and apply work instructions for the allotted task
- 1.3 Obtain, confirm and apply safety requirements from the site safety plan and organisational policies and procedures relevant to the allotted task
- 1.4 Identify, confirm and apply environmental protection requirements for the allotted task from the project environmental management plan
- 1.5 Mark out saw-cuts in accordance with specifications
2. Select and operate concrete saw
- 2.1 Select concrete saw consistent with needs of job and in accordance with standard work practice, and report any faults
- 2.2 Checkequipment for serviceability and safety, and report faults
- 2.3 Clear route of hazards for safe placement of hoses
- 2.4 Assess concrete for optimum timing of saw-cut
- 2.5 Connect hoses to tool and cover trip hazards
- 2.6 Use concrete saw safely and effectively in application processes
- 2.7 Locate concrete saw safely when not in use
- 2.8 Saw and cut to correct dimensions as specified
- 2.9 Clean out and protect open cut
- 2.10 Complete saw cutting records
3. Clean up
- 3.1 Clear work area and dispose of or recycle materials in accordance with project environmental management plan
- 3.2 Clean, check, maintain and store machinery, tools and equipment in accordance with manufacturer’s recommendations and standard work practices
Relevant compliance documentation
may include:
legislative, organisation and site requirements and procedures
manufacturer’s guidelines and specifications
Australian standards
code of practice
Employment and workplace relations legislation
Equal Employment Opportunity and Disability Discrimination legislation
Work instructions may include:
verbal or written and graphical instructions, signage, work schedules/plans/specifications, work bulletins, charts and hand drawings, memos, materials safety data sheets (MSDS) and diagrams or sketches
plans and specifications
quality requirements, including: dimensions and tolerances, standards of work and material standards
safe work procedures or equivalent related to using hand and power tools
Safety requirements may include:
protective clothing and equipment
use of tools and equipment
workplace environment and safety
handling of materials
hazard control
hazardous materials and substances
emergency procedures related to equipment operation which may include
emergency shutdown and stopping
extinguishing equipment fires
organisational first aid requirements and
evacuation
Environmental protection requirements may include:
organisational/project environmental management plan
waste management
water quality protection
noise
vibration
dust and
clean-up management
Checking tools is to include:
checking of electrical safety/inspection tag for currency
equipment defect identification
assessment of conditions and hazards and determination of work requirements
Power tools may include those powered by but not limited to:
240 volt electricity (circular saw, mitre saw, drill, grinder, impact hammer)
pneumatic (wrench, grinder, jackhammer, screwdriver)
battery driven (drill, grinder, circular saw, sander, impact hammer) and
hydraulics (portapower and attachments, jacking equipment, shoring systems)
Concrete saws are to include:
wet cut
cut off saws
early dry cut
Equipment is to include:
air hoses
generator
electric leads
may include:
legislative, organisation and site requirements and procedures
manufacturer’s guidelines and specifications
Australian standards
code of practice
Employment and workplace relations legislation
Equal Employment Opportunity and Disability Discrimination legislation
Work instructions may include:
verbal or written and graphical instructions, signage, work schedules/plans/specifications, work bulletins, charts and hand drawings, memos, materials safety data sheets (MSDS) and diagrams or sketches
plans and specifications
quality requirements, including: dimensions and tolerances, standards of work and material standards
safe work procedures or equivalent related to using hand and power tools
Safety requirements may include:
protective clothing and equipment
use of tools and equipment
workplace environment and safety
handling of materials
hazard control
hazardous materials and substances
emergency procedures related to equipment operation which may include
emergency shutdown and stopping
extinguishing equipment fires
organisational first aid requirements and
evacuation
Environmental protection requirements may include:
organisational/project environmental management plan
waste management
water quality protection
noise
vibration
dust and
clean-up management
Checking tools is to include:
checking of electrical safety/inspection tag for currency
equipment defect identification
assessment of conditions and hazards and determination of work requirements
Power tools may include those powered by but not limited to:
240 volt electricity (circular saw, mitre saw, drill, grinder, impact hammer)
pneumatic (wrench, grinder, jackhammer, screwdriver)
battery driven (drill, grinder, circular saw, sander, impact hammer) and
hydraulics (portapower and attachments, jacking equipment, shoring systems)
Concrete saws are to include:
wet cut
cut off saws
early dry cut
Equipment is to include:
air hoses
generator
electric leads
Critical aspects for assessment and evidence required to demonstrate competency in this unit
The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:
knowledge of the requirements, procedures and instructions for the use of concrete saws on pavements
implementation of requirements, procedures and techniques for the safe, effective and efficient use of cutting and sawing concrete pavements
consistent timely use of concrete saws to safely, effectively and efficiently meets the required outcomes
conduct sawing on concrete pavements to a minimum of 100 linear metres
Context of and specific resources for assessment
This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.
The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.
Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.
Aboriginal people and other people from a non Englishspeaking background may have second language issues.
Assessment of this competency requires typical resources normally used in the work environment. Selection and use of resources for particular worksites may differ due to site circumstances.
Where applicable, physical resources should include equipment modified for people with disabilities.
Access must be provided to appropriate learning and/or assessment support when required.
Method of assessment
This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:
written and/or oral assessment of the candidate’s required knowledge
observed, documented and/or first hand testimonial evidence of the candidate’s:
implementation of appropriate requirement, procedures and techniques for the safe, effective and efficient achievement of required outcomes
consistently achieving the required outcomes
first hand testimonial evidence of the candidate’s:
working with others to undertake the use of concrete saws to initiate planned cracks
Guidance information for assessment
Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.
The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:
knowledge of the requirements, procedures and instructions for the use of concrete saws on pavements
implementation of requirements, procedures and techniques for the safe, effective and efficient use of cutting and sawing concrete pavements
consistent timely use of concrete saws to safely, effectively and efficiently meets the required outcomes
conduct sawing on concrete pavements to a minimum of 100 linear metres
Context of and specific resources for assessment
This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.
The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.
Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.
Aboriginal people and other people from a non Englishspeaking background may have second language issues.
Assessment of this competency requires typical resources normally used in the work environment. Selection and use of resources for particular worksites may differ due to site circumstances.
Where applicable, physical resources should include equipment modified for people with disabilities.
Access must be provided to appropriate learning and/or assessment support when required.
Method of assessment
This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:
written and/or oral assessment of the candidate’s required knowledge
observed, documented and/or first hand testimonial evidence of the candidate’s:
implementation of appropriate requirement, procedures and techniques for the safe, effective and efficient achievement of required outcomes
consistently achieving the required outcomes
first hand testimonial evidence of the candidate’s:
working with others to undertake the use of concrete saws to initiate planned cracks
Guidance information for assessment
Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.