Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Provide design documentation and review and support fire system installation processes

Provide design documentation and review and support fire system installation processes

Unit of competency
National Code
CPCSFS5011A
State Code
WA416
TGA Status
Replaced
DTWD Status
Transition (Replaced)
Current Release Number
1.00
Current Release Date
19/05/2011
State Implementation and Classification
Approved Date
27/04/2011
Field of Education
039905 - Fire Technology
Original Release Date
27/04/2011
Nominal Hours
55
Description
This unit of competency specifies the outcomes required to develop detailed drawings and notes for the fire systems installation team from approved detailed fire systems design drawings. The unit also covers the outcomes required to assist and support the installation team when changes to detailed designs may be required owing to contingencies encountered on-site.Licensing, legislative, regulatory or certification requirements may apply to this unit and so the varying state or territory requirements should be confirmed with the relevant body.
Notes
Elements and Performance Criteria
1. Produce installation drawings and documentation.
  • 1.1. Approved detailed design drawings of fire systems are checked to ensure that installation implications of required changes have been addressed.
  • 1.2. Approved detailed design drawings of fire systems are used to create installation drawings.
  • 1.3. Detailed design specifications of fire systems are used to notate the installation drawings with the location of specific components of the fire system.
2. Review drawings prior to installation.
  • 2.1. Ongoing changes to detailed structural or other services' design drawings are regularly monitored and recorded.
  • 2.2. The impact of structural and other services design changes on fire systems design and installation is considered and appropriate solutions are proposed and negotiated with relevant project team members, as required.
  • 2.3. Fire systems installation drawings and documentation are amended to incorporate accepted solutions according to workplace and project procedures.
3. Resolve on-site installation problems.
  • 3.1. Notifications of on-site installation issues are recorded, prioritised and considered in line with project timeframes.
  • 3.2. Appropriate solutions are proposed and negotiated with relevant project team members, as required.
  • 3.3. Fire systems installation drawings and documentation are amended to incorporate accepted solutions.
  • 3.4. Solutions are communicated to on-site fire system installation team members and amended documentation is supplied according to workplace and project procedures.
RANGE STATEMENT
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Installation implications may include:
on-site health and safety risks, such as:
manual handling
confined spaces
working at height
constraints relating to access, such as:
height of pipe
length of pipe
distance from beams
distance from walls.
Monitoring project drawings and documentation may involve:
regular review of project management software tools and systems
regular review of emails
telephone communication with project team, including:
architect
lead contractor
other service contractors.
On-site installation issues may include:
discrepancies between designed and actual structure
discrepancies between designed and actual systems for other services, including:
mechanical
hydraulic
electrical
errors in supplied materials and components
scheduling and sequencing changes
problems with access to installation locations of fire system components.
EVIDENCE GUIDE
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed in the workplace or a close simulation of the workplace environment, provided that the simulated or project-based assessment fully replicates workplace conditions, materials, activities, responsibilities and procedures.
This unit could be assessed as an activity involving the preparation of accurate documentation and provision of ongoing support for the installation of fire systems in a range of projects and buildings.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person who demonstrates competency in this unit must be able to provide evidence of the required skills and knowledge specified within this unit.
In particular the person should demonstrate:
the ability to:
read and interpret a range of design drawings
create, manipulate, save, file and share design drawings
an understanding of technical issues impacting on the installation of fire systems
high-level communication skills to interact with on-site installers, and other service contractors and consultants
an understanding of the relevant regulatory approval and fire systems design certification processes
the ability to problem-solve and negotiate to produce appropriate design solutions for issues and contingencies encountered at the installation phase of a range of fire systems in different buildings, including:
low-rise buildings
medium-rise buildings
high-rise buildings (over 25 metres)
buildings over 45 metres in height.
Context of and specific resources for assessment
Assessment of essential underpinning knowledge may be conducted in an off-site context. It is to comply with relevant regulatory or Australian standards' requirements.
Resource implications for assessment include:
design briefs, drawings, plans and specifications
copies of codes, standards, legislation and regulatory requirements
access to information and communications technology - hardware and software
access to manufacturer's information regarding fittings and components.
Method of assessment
Assessment must:
satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package
include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
reinforce the integration of employability skills with workplace tasks and job roles
confirm that competency is verified and able to be transferred to other circumstances and environments.
Guidance information for assessment
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Replaced By
State Code National Code Title Type
OCM35 CPCSFS5011 Provide design documentation and review and support fire system installation processes Unit of competency
State Code National Code Title Type
W713 CPC50509 Diploma of Fire Systems Design Qualification