Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Mix and apply thin-film rollcoat resin flooring systems

Mix and apply thin-film rollcoat resin flooring systems

Unit of competency
National Code
MSFFL3072
State Code
OAJ58
TGA Status
Current
DTWD Status
Approved
Current Release Number
1.00
Current Release Date
03/12/2018
State Implementation and Classification
Approved Date
22/05/2019
Field of Education
040321 - Floor Coverings
Original Release Date
22/05/2019
Nominal Hours
30
Description
This unit describes the skills and knowledge required to prepare and apply thin-film rollcoat resin flooring systems. This unit applies to flooring technicians working in accordance with pre-determined work orders.Licensing, legislative or certification requirements may apply to this unit and relevant state/territory and local government agencies should be consulted to determine any necessary certification or licensing for undertaking flooring work. Access to construction sites requires certification of general induction training specified by the National Code for Induction for Construction Work (ASCC 2007).
Notes
Elements and Performance Criteria
1. Prepare for work
  • 1.1 Identify and follow work health and safety legislative, and organisational requirements
  • 1.2 Correctly interpret work orders and confirm job requirements
  • 1.3 Select and check tools and equipment for suitability, serviceability and safety prior to use
  • 1.4 Plan application with respect to specified film thickness and/or consumption, cutting in, boundaries, seams, joints and exit points
2. Prepare substrate
  • 2.1 Inspect condition of the mechanically prepared subfloor and confirm suitability for required finish consistent with manufacturer recommendations
  • 2.2 Remove dust and debris from the substrate prior to application, and control sources
3. Set out work area
  • 3.1 Establish mixing area in suitable area and select surface protection measures and apply to areas not being coated
  • 3.2 Check coating materials for correct quantities, undamaged packaging and no obvious discrepancies in colour and viscosity
  • 3.3 Select suitable masking tape and correctly apply to mark off edges, transitions and other floor boundaries
4. Prepare rollcoat system
  • 4.1 Correctly fit personal protective equipment (PPE) before coating materials are handled
  • 4.2 Accurately measure and mix component quantities in accordance with supplier instructions
5. Apply rollcoat system
  • 5.1 Apply mixed basecoat in accordance with supplier application notes
  • 5.2 Prepare cured basecoat for topcoat application in accordance with supplier application notes
  • 5.3 Apply mixed topcoat in accordance with supplier application notes
  • 5.4 Check coating applications for quality at each stage and rectify any deficiencies
6. Complete housekeeping
  • 6.1 Check, clean and store tools and equipment in accordance with workplace procedures
  • 6.2 Seal and store unused coating materials in accordance with supplier instructions
  • 6.3 Clean work area and dispose of rubbish safely
  • 6.4 Accurately complete required workplace and project documentation