Unit of competency Outline

Date retreived
22/07/2026 6:16 AM AWST

Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Organise and implement ESI line and easement surveys

Organise and implement ESI line and easement surveys

Unit of competency
National Code
UETDRDS013
State Code
ODM86
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
20/09/2021
State Implementation and Classification
Approved Date
21/12/2021
Field of Education
031101 - Surveying
Original Release Date
21/12/2021
Nominal Hours
126
Description
This unit covers the surveying of distribution and sub-transmission lines and easements for activities associated with the design and installation of electrical equipment. This activity encompasses the use of instruments, such as compasses, inclinometer and distance measuring devices, in accordance with customer requirements, nominated design specifications and company processes.The application of the skills and knowledge described in this unit may require a licence/registration to practice in the workplace subject to regulations for undertaking of electrical work. Other conditions may apply under state and territory legislative and regulatory licensing requirements which must be confirmed prior to commencing this unit.
Notes
Elements and Performance Criteria
1 Plan and coordinate the organisation and implementation of line and easement surveys
  • 1.1 Work health and safety (WHS)/occupational health and safety (OHS) practices/procedures and environmental and sustainable energy procedures, which may influence the organisation and implementation of line and easement surveys, are reviewed and determined
  • 1.2 Purpose of the line and easement surveys is established and expected outcomes of the work are confirmed with appropriate personnel
  • 1.3 Organisational established procedures on policies and specifications for the design are obtained or established with appropriate personnel
  • 1.4 Equipment/tools and personnel protective equipment (PPE) are selected and coordinated based on specified requirements and established procedures
  • 1.5 Work is prioritised and sequenced for the most efficient and effective outcome following consultation with others for completion within acceptable timeframes, to a quality standard and in accordance with established procedures
  • 1.6 Risk control measures are identified, prioritised and evaluated against the work schedule
  • 1.7 Relevant work permits are secured to coordinate the performance of work according to requirements and/or established procedures
  • 1.8 Resources, including personnel, equipment, tools and PPE, required for the job are identified, scheduled and coordinated and confirmed safe and in technical working order
  • 1.9 Liaison and communication issues with others/authorised personnel, authorities, clients and landowners are resolved and activities coordinated to carry out work
  • 1.10 Site is prepared according to the work schedule and to minimise risk and damage to property, commerce and individuals in accordance with established procedures
  • 1.11 Personnel participating in the work, including plant operators and contractors, are fully briefed and respective responsibilities coordinated and authorised, where applicable, in accordance with established procedures
  • 1.12 Positioning of road signs, barriers and warning devices is planned in accordance with requirements
2 Carry out and coordinate the organisation and implementation of line and easement surveys
  • 2.1 Circuit/systems modelling is used to evaluate alternative proposals in accordance with established procedures
  • 2.2 WHS/OHS and sustainable energy principles, functionality and practices to reduce the incidence of accidents and minimise waste are incorporated into the project in accordance with requirements and/or established procedures
  • 2.3 Survey project decisions are made on the basis of safety and effective outcomes according to requirements and/or established procedures
  • 2.4 Mathematical models of the distribution system are used to analyse the effectiveness of the finished project in accordance with requirements and established procedures
  • 2.5 Technical advice is given to potential hazards, safety risks and control measures so that monitoring and preventative action can be undertaken and/or appropriate authorities consulted, where necessary, in accordance with requirements and established procedures
  • 2.6 Essential knowledge and associated skills are applied to analyse specific data and compare it with compliance specifications to ensure completion of the project within an agreed timeframe according to requirements
  • 2.7 Solutions to non-routine problems are identified and actioned using acquired essential knowledge and associated skills according to requirements
  • 2.8 Quality of work is monitored against personal performance agreement and/or established organisational and professional standards
  • 2.9 Work teams/groups are arranged/coordinated/evaluated to ensure planned goals are met according to established procedures
3 Complete and coordinate the organisation and implementation of line and easement surveys
  • 3.1 Final assessment of the surveys is undertaken to ensure they comply with all requirements and include all specifications and documentations needed to complete the design brief
  • 3.2 Appropriate personnel are notified of completion and reports and/or completion documents are finalised
  • 3.3 Reports and/or completion documents are submitted to relevant personnel/organisations for approval and, where applicable, statutory or regulatory approval
  • 3.4 Approved copies of survey documents are issued and records are updated in accordance with established procedures
No information
No information
Replaces
State Code National Code Title Type
OBI04 UETTDRDS45 Organise and implement ESI line and easement surveys Unit of competency
Replaced By
State Code National Code Title Type
OED87 UETDRDS016 Coordinate and perform line and easement surveys Unit of competency