Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Install resilient floor coverings using custom designs and decorative finishes
Install resilient floor coverings using custom designs and decorative finishes
Unit of competency
National Code
LMFFL3303A
LMFFL3303A
State Code
W8564
W8564
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
19/06/2009
Field of Education
040321 - Floor Coverings
Original Release Date
19/06/2009
Nominal Hours
40
Description
This unit covers the competency to install resilient sheet floor coverings using custom design, mechanically and hand cut motifs, logos and decorative finishes.
Notes
Elements and Performance Criteria
1. Prepare for installation
- 1.1. Applicable legislative, OHS and organisational requirements relevant to installing resilient floor coverings are verified and complied with
- 1.2. Instructions and/or plans are read and interpreted to identify process required to complete work tasks
- 1.3. Sub-floor condition is assessed for suitability for installation of custom design resilient floor coverings
- 1.4. Suitable adhesives, trims and accessories are selected
- 1.5. Tools, equipment and materials are selected and checked prior to use to ensure that they are appropriate for the work, serviceable and in a safe condition
- 1.6. Sequence of work is planned, including the starting point, to ensure efficiency and quality of installation
2. Set out materials
- 2.1. Resilient floor coverings to be installed are checked against order
- 2.2. Resilient custom design floor coverings are acclimatised according to manufacturers' recommendations
- 2.3. Resilient custom design floor coverings for fixing are organised and used in accordance with relevant safety management requirements
- 2.4. Working lines and starting point are established and marked on the sub-floor
- 2.5. Motifs, logos or custom designs are set out and marked on the sub-floor
3. Lay floor covering
- 3.1. Instructions and sequence for laying and fixing is followed
- 3.2. Resilient custom design floor coverings are laid out to meet directional sequence, pattern match, and specification requirements and to minimise waste and joins as appropriate
- 3.3. Resilient custom design flooring materials are accurately and clearly marked for cutting
- 3.4. Resilient custom design floor coverings are cut to required shape ensuring minimum waste
- 3.5. Materials for fixing are organised and used in accordance with relevant safety management requirements
- 3.6. Adhesives and edge strips/accessories are prepared for use as required
- 3.7. Welding and fixing methods and equipment are used following manufacturer instructions
- 3.8. Finished job is inspected and any imperfections are rectified following workplace procedures
4. Complete housekeeping
- 4.1. Unused materials are stored or recycled as required
- 4.2. Tools and equipment are cleaned and stored appropriately
- 4.3. Work area is cleaned and rubbish disposed of appropriately
- 4.4. Workplace documentation and/or reports are completed
RANGE STATEMENT
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Legislative requirements
are to be in accordance with applicable legislation from all levels of government that affect organisational operation. Requirements may include but not be limited to award and enterprise agreements, industrial relations, Australian Standards, confidentiality and privacy, OHS, the environment, equal opportunity, anti-discrimination, relevant industry codes of practice, duty of care and heritage
OHS requirements
are to be in accordance with Commonwealth, State or Territory legislation and regulations, organisational safety policies and procedures. Requirements may include but not be limited to the use of personal protective equipment and clothing, fire fighting equipment, First Aid equipment, hazard and risk control and elimination, control of hazardous materials and substances, manual handling including lifting and carrying
Organisational requirements
may include but not be limited to legal, organisational and site guidelines, policies and procedures relating to own role and responsibility, quality assurance, procedural manuals, quality and continuous improvement processes and standards, OHS, emergency and evacuation, ethical standards, recording and reporting, access and equity principles and practices, equipment use, maintenance and storage, environmental management (waste disposal, recycling and re-use guidelines)
Resilient flooring coverings
may include:
homogenous/heterogeneous
linoleum sheet
encapsulated glass fibre
in laid
rotogravure
Instructions
Workplace procedures relating to the use and operation of tools and equipment
Workplace instructions, including job sheets, plans, drawings and designs
Workplace procedures relating to reporting and communications
Adhesives
may include plasticised and rubber resign acrylic, two part epoxy, poly-methane and water based and solvent based contact adhesive
Tools and equipment
are to include utility knife and hook, straight and concave blades, straight edge square, square, chalk and chalk-line, tape measure, hacksaw, serrated trowel, hammer, seam and edge trimmer, recess scriber and pre-formed linoleum recess scribers, scribing bar, welding gun and accessories, hot air gun, grooving tool, divider, pencil cove roller, hand roller, cover gauging tool, roller, gas bottle and gun, rubber mallet, paint brush and bucket, spatula knife, builders pencil, contact bucket, linoleum trolley, liquid seam sealer, seam sealer applicator and wall trimmer
Materials
are to include but are not limited to resilient sheet flooring, skirting, reducing and edge strips, welding rod, coving accessories, tapes, pattern paper and adhesives
Welding
is to include hot welding and chemical welding
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Legislative requirements
are to be in accordance with applicable legislation from all levels of government that affect organisational operation. Requirements may include but not be limited to award and enterprise agreements, industrial relations, Australian Standards, confidentiality and privacy, OHS, the environment, equal opportunity, anti-discrimination, relevant industry codes of practice, duty of care and heritage
OHS requirements
are to be in accordance with Commonwealth, State or Territory legislation and regulations, organisational safety policies and procedures. Requirements may include but not be limited to the use of personal protective equipment and clothing, fire fighting equipment, First Aid equipment, hazard and risk control and elimination, control of hazardous materials and substances, manual handling including lifting and carrying
Organisational requirements
may include but not be limited to legal, organisational and site guidelines, policies and procedures relating to own role and responsibility, quality assurance, procedural manuals, quality and continuous improvement processes and standards, OHS, emergency and evacuation, ethical standards, recording and reporting, access and equity principles and practices, equipment use, maintenance and storage, environmental management (waste disposal, recycling and re-use guidelines)
Resilient flooring coverings
may include:
homogenous/heterogeneous
linoleum sheet
encapsulated glass fibre
in laid
rotogravure
Instructions
Workplace procedures relating to the use and operation of tools and equipment
Workplace instructions, including job sheets, plans, drawings and designs
Workplace procedures relating to reporting and communications
Adhesives
may include plasticised and rubber resign acrylic, two part epoxy, poly-methane and water based and solvent based contact adhesive
Tools and equipment
are to include utility knife and hook, straight and concave blades, straight edge square, square, chalk and chalk-line, tape measure, hacksaw, serrated trowel, hammer, seam and edge trimmer, recess scriber and pre-formed linoleum recess scribers, scribing bar, welding gun and accessories, hot air gun, grooving tool, divider, pencil cove roller, hand roller, cover gauging tool, roller, gas bottle and gun, rubber mallet, paint brush and bucket, spatula knife, builders pencil, contact bucket, linoleum trolley, liquid seam sealer, seam sealer applicator and wall trimmer
Materials
are to include but are not limited to resilient sheet flooring, skirting, reducing and edge strips, welding rod, coving accessories, tapes, pattern paper and adhesives
Welding
is to include hot welding and chemical welding
EVIDENCE GUIDE
The Evidence Guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Comply with legislation, regulations, standards, codes of practice and established safe practices and procedures for installing resilient floor coverings
Interpret work order and locate and apply relevant information
Apply safe handling requirements for equipment, products and materials, including use of personal protective equipment
Follow work instructions, operating procedures and inspection practices to:
minimise the risk of injury to self and others
prevent damage to goods, equipment and products
maintain required production output and product quality
Cut and lay resilient floor coverings using custom designs and decorative finishes with internal and external mitres:
one piece and performed coving; and
custom designed and pattern scribed coving using commercial grade resilient floor coverings
Cut and lay resilient floor coverings using custom design containing logo/motifs using commercial grade resilient floor coverings including decorative welding, inlays and borders
Context of, and specific resources for assessment
The application of competency is to be assessed in the workplace or realistically simulated workplace
Assessment is to occur under standard and authorised work practices, safety requirements and environmental constraints
Assessment of essential underpinning knowledge, other than confirmatory questions, will usually be conducted in an off-site context
Assessment is to comply with relevant regulatory or Australian Standards requirements
The following resources should be made available:
workplace location or simulated workplace
materials and equipment relevant to installing resilient floor coverings using custom designs and decorative finishes
specifications and work instructions
Method of assessment
Assessment must satisfy the endorsed assessment guidelines of the Furnishing Industry Training Package
Assessment methods must confirm consistency and accuracy of performance (over time and in a range of workplace relevant contexts) together with application of underpinning knowledge
Assessment methods must be by direct observation of tasks and include questioning on underpinning knowledge to ensure its correct interpretation and application
Assessment may be applied under project related conditions (real or simulated) and require evidence of process
Assessment must confirm a reasonable inference that competency is able not only to be satisfied under the particular circumstance, but is able to be transferred to other circumstances
Assessment may be in conjunction with assessment of other units of competency
The Evidence Guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Comply with legislation, regulations, standards, codes of practice and established safe practices and procedures for installing resilient floor coverings
Interpret work order and locate and apply relevant information
Apply safe handling requirements for equipment, products and materials, including use of personal protective equipment
Follow work instructions, operating procedures and inspection practices to:
minimise the risk of injury to self and others
prevent damage to goods, equipment and products
maintain required production output and product quality
Cut and lay resilient floor coverings using custom designs and decorative finishes with internal and external mitres:
one piece and performed coving; and
custom designed and pattern scribed coving using commercial grade resilient floor coverings
Cut and lay resilient floor coverings using custom design containing logo/motifs using commercial grade resilient floor coverings including decorative welding, inlays and borders
Context of, and specific resources for assessment
The application of competency is to be assessed in the workplace or realistically simulated workplace
Assessment is to occur under standard and authorised work practices, safety requirements and environmental constraints
Assessment of essential underpinning knowledge, other than confirmatory questions, will usually be conducted in an off-site context
Assessment is to comply with relevant regulatory or Australian Standards requirements
The following resources should be made available:
workplace location or simulated workplace
materials and equipment relevant to installing resilient floor coverings using custom designs and decorative finishes
specifications and work instructions
Method of assessment
Assessment must satisfy the endorsed assessment guidelines of the Furnishing Industry Training Package
Assessment methods must confirm consistency and accuracy of performance (over time and in a range of workplace relevant contexts) together with application of underpinning knowledge
Assessment methods must be by direct observation of tasks and include questioning on underpinning knowledge to ensure its correct interpretation and application
Assessment may be applied under project related conditions (real or simulated) and require evidence of process
Assessment must confirm a reasonable inference that competency is able not only to be satisfied under the particular circumstance, but is able to be transferred to other circumstances
Assessment may be in conjunction with assessment of other units of competency
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| W0199 | LMFFC3010A | Install welded resilient flooring | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| WI371 | MSFFL3014 | Install resilient floor coverings using custom designs and decorative finishes | Unit of competency |