Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Install battery storage equipment power conversion equipment to grid
Install battery storage equipment power conversion equipment to grid
Unit of competency
National Code
UEERE0077
UEERE0077
State Code
OEU94
OEU94
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
16/03/2023
Field of Education
031399 - Electrical And Electronic Engineering And Technology, N.e.c.
Original Release Date
16/03/2023
Nominal Hours
27
Description
This unit involves the skills and knowledge required to install battery storage equipment power conversion equipment (PCE) to grid.It includes working safely and to industry installation standards, placing and securing system components accurately, making required circuit connections and completing the necessary installation documentation.The skills and knowledge described in this unit require a licence or permit to practice in the workplace where work is carried out on electrical installations, which are designed to operate at voltages greater than 50 volt (V) alternating current (a.c.) or 120 V direct current (d.c.).Competency development activities in this unit are subject to regulations directly related to licensing. Where a licence or permit to practice is not held, a relevant contract of training, such as an Australian Apprenticeship, is required.Additional and/or other conditions may apply in some jurisdictions subject to regulations related to electrical work. Practice in the workplace and during training is also subject to work health and safety (WHS)/occupational health and safety (OHS) regulations.Note: Those holding an Unrestricted Electrician’s Licence or equivalent issued in an Australian state or territory meet the prerequisite requirements of UEEEL0012 Install low voltage wiring, appliances, switchgear and associated accessories. All other prerequisite requirements must be met.
Notes
Elements and Performance Criteria
1 Plan for the installation of battery storage equipment PCE to grid
- 1.1 Nature of the installation is verified from design documentation and any design concerns identified are referred to designer
- 1.2 WHS/OHS processes and procedures for work are identified and applied in accordance with workplace procedures
- 1.3 Hazards associated with battery storage systems are identified and the risk control measures are listed in safe work method statements/job safety analysis
- 1.4 Work is planned in consultation with the customer and others impacted by the work and sequenced appropriately
- 1.5 Designer recommendations, relevant industry standards, regulations and manufacturer specifications are identified and applied to planning the system installation
- 1.6 Materials, tools, equipment and measuring devices required for installation are obtained in accordance with workplace procedures and checked for correct operation and safety
- 1.7 Live testing, measurement and isolation requirements determined and applied in accordance with WHS/OHS requirements and workplace procedures
2 Install battery storage equipment PCE to grid
- 2.1 Job safety analysis is undertaken or safe work method statement is prepared and used to inform work processes in accordance with regulations and workplace procedures
- 2.2 Energy storage system components are installed in compliance with industry standards, regulations and job/manufacturer specifications, and with sufficient access to enable terminations, adjustment and maintenance
- 2.3 Wiring is terminated at components and associated equipment in accordance with manufacturer specifications and functional and regulatory requirements
- 2.4 System components are programmed in accordance with design, relevant industry standards, regulations and manufacturer specifications
- 2.5 Quality checks of installed apparatus are conducted in accordance with workplace procedures
- 2.6 Testing and commissioning of the system is conducted in accordance with design documentation, regulations, relevant industry standards and manufacturer specifications
- 2.7 Worksite is cleaned and made safe in accordance with workplace procedures
- 2.8 ‘As-installed’ system and associated equipment are documented, manuals produced, and system is handed over to required person/s as per legislation, regulations, industry standards and job requirements
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| BBB22 | UEERE4001 | Install, maintain and fault find battery storage systems for grid-connected photovoltaic systems | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BIV5 | UEE43322 | Certificate IV in Electrical - Renewable Energy | Qualification |
| BFN0 | UEE30820 | Certificate III in Electrotechnology Electrician | Qualification |
| AF113 | UEESS00191 | Grid-connected Battery Storage Systems Designer-Installer Skill Set | Skill set |
| AF123 | UEESS00192 | Grid-connected Battery Storage Systems Installer Skill Set | Skill set |
| BIV3 | UEE50722 | Diploma of Renewable Energy Engineering | Qualification |