Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Perform advanced tilt-up slab erection

Perform advanced tilt-up slab erection

Unit of competency
National Code
CPCCRI3015
State Code
OCP94
TGA Status
Current
DTWD Status
Approved
Current Release Number
3.00
Current Release Date
24/12/2024
State Implementation and Classification
Approved Date
01/06/2021
Field of Education
040399 - Building, N.e.c.
Original Release Date
01/06/2021
Nominal Hours
32
Description
This unit specifies the skills and knowledge required to conduct advanced tilt-up slab erection, and to coordinate the slinging, stability, lifting, moving, placement and storage of slabs in conjunction with the crane operator. It includes selection of equipment, and load distribution and calculation.It applies to workers who perform advanced tilt-slab erection, and who would be expected to take responsibility for organising and completing these tasks with a high degree of self direction.Completion of the general construction induction training program, specified in the Safe Work Australia model Code of Practice: Construction Work, is required by anyone carrying out construction work. Achievement of CPCWHS1001 Prepare to work safely in the construction industry meets this requirement.Licensing, legislative, regulatory or certification requirements apply to this unit of competency in some states and territories. For further information, check with the relevant regulatory authority.
Notes
Elements and Performance Criteria
1 Plan and prepare to perform advanced tilt-up slab erection.
  • 1.1 Interpret work instructions and associated documentation and clarify requirements with relevant persons.
  • 1.2 Plan all work to comply with relevant legislation, regulations, standards, codes, work health and safety, environmental and workplace requirements.
  • 1.3 Select plant, tools and equipment required for work tasks, check for serviceability and rectify or report identified faults.
  • 1.4 Calculate materials quantities.
  • 1.5 Acquire materials for task and locate them safely ready for use.
2 Select and check equipment.
  • 2.1 Erect required safety signage and barricades and fit personal protective equipment (PPE).
  • 2.2 Select resources, materials and equipment in accordance with load charts and inspect for compliance with work instructions.
  • 2.3 Inspect lifting equipment in accordance with manufacturer and workplace requirements.
  • 2.4 Label, reject and dispose of any lifting and load-shifting equipment identified as inconsistent with manufacturer requirements, to prevent its use in any circumstance.
  • 2.5 Select elevated work platforms and other means of mechanical access systems as specified.
  • 2.6 Install fall arrest equipment.
  • 2.7 Select personnel cartage systems.
3 Erect tilt-up slabs.
  • 3.1 Review lift plan and determine job sequencing schedule and documentation, and communicate this information to relevant persons to ensure coordination.
  • 3.2 Calculate and confirm load mass and load distribution.
  • 3.3 Determine erection sequence for tilt-up slab components.
  • 3.4 Assemble and erect lifting or pulling devices for movement of loads.
  • 3.5 Sling load.
  • 3.6 Shift load in accordance with job safety and environmental analysis (JSEA) and safe work method statement (SWMS).
  • 3.7 Maintain stability of load during lifting, tilting and transportation.
  • 3.8 Direct load to landing position in accordance with engineering specifications.
4 Position and anchor tilt-up slabs.
  • 4.1 Position tilt slab components in accordance with engineering specifications.
  • 4.2 Achieve shape of structure by checking dimensions and applying temporary bracing.
  • 4.3 Anchor tilt slab components in accordance with manufacturer requirements and engineering specifications.
5 Remove rigging equipment.
  • 5.1 Dismantle lifting/shifting equipment and packing, return to resting position and inspect for wear.
  • 5.2 Complete logbook and site records in accordance with workplace requirements.
6 Clean up.
  • 6.1 Clear work area and dispose of, reuse or recycle materials in accordance with regulatory and workplace requirements.
  • 6.2 Clean, check, maintain and store tools and equipment in accordance with manufacturer and workplace requirements.
No information
No information
Replaces
State Code National Code Title Type
D7402 CPCCRI3015A Perform advanced tilt-up slab erection Unit of competency
State Code National Code Title Type
BGB5 CPC30720 Certificate III in Rigging Qualification