Unit of competency Outline

Date retreived
22/07/2026 3:38 PM AWST

Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Plan and organise work

Plan and organise work

Unit of competency
National Code
CPCCCM1013
State Code
OAP21
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
17/01/2019
State Implementation and Classification
Approved Date
12/04/2019
Field of Education
120505 - Work Practices Programmes
Original Release Date
12/04/2019
Nominal Hours
16
Description
This unit specifies the skills and knowledge required to plan and organise individual and group work activities on a construction site. It includes: identifying task requirementsplanning steps and organising workprioritising work tasks organising time and resources to undertake given tasks effectively and cooperatively with other team members.The unit supports the attainment of basic planning and organisational skills and knowledge by workers within the construction industry. It applies to workers in the construction industry. It involves working under supervision in a team environment.No licensing, legislative, or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1. Identify work task requirements.
  • 1.1 Read and/or interpret a work order
  • 1.2 Determine work task requirements, work health and safety (WHS) requirements, and appropriate tools and equipment for the work.
  • 1.3 Confirm and clarify work task requirements, WHS requirements, and tools and equipment with supervisor to ensure correct interpretation of requirements.
2. Plan steps to complete work task requirements.
  • 2.1 Analyse task and identify work steps to ensure efficient conduct of work in accordance with identified WHS, environmental and quality requirements.
  • 2.2 Plan task steps in conjunction with team members.
3. Organise and resource work task.
  • 3.1 Work with team members to sequence work task steps, and to allocate time and resources to each step.
  • 3.2 Complete records of task planning and of task progress in accordance with workplace requirements.
4. Review work task planning and organising process.
  • 4.1 Review planning and organising of work task activities to establish the effectiveness of the process.
  • 4.2 Provide feedback and suggestions for improvements, and consider them in future planning and organising of work task activities.
No information
No information
Replaces
State Code National Code Title Type
D7348 CPCCCM1013A Plan and organise work Unit of competency
Replaced By
State Code National Code Title Type
OCP77 CPCCOM1013 Plan and organise work Unit of competency
State Code National Code Title Type
BEG4 CPC30318 Certificate III in Concreting Qualification
BCX38 52807WA Certificate I in Industrial Skills (Entry Level Training) Accredited course