Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Arrange resources and prepare for the building or construction project

Arrange resources and prepare for the building or construction project

Unit of competency
National Code
CPCCBC4017A
State Code
W9254
TGA Status
Replaced
DTWD Status
Transition (Replaced)
Current Release Number
1.00
Current Release Date
19/05/2011
State Implementation and Classification
Approved Date
20/10/2009
Field of Education
040303 - Building Construction Management
Original Release Date
20/10/2009
Nominal Hours
20
Description
This unit of competency specifies the outcomes required to procure the physical and human resources necessary to ensure the development of on-site facilities and the availability of personnel, plant and equipment, materials and other site-essential items for low rise (low rise' licensing classification with reference to Class 1 and 10 construction and Classes 2 to 9 with a gross floor area not exceeding 2000 square metres, not including Type A or Type B construction) construction projects. Knowledge of physical resource acquisition and supply processes, and identification and procurement of suitable labour through the organisation's own employees and/or subcontractors is essential.
Notes
Elements and Performance Criteria
1. Notify client and relevant authorities and agencies of the schedule of works.
  • 1.1. Fees due are paid and site handover date is confirmed with client.
  • 1.2. Insurance and security requirements are established and provided.
  • 1.3. Parking restrictions are determined and advised to relevant personnel.
  • 1.4. Authorities requiring formal notification of the commencement of work are contacted.
2. Organise the delivery of on-site accommodation and facilities.
  • 2.1. Requirements for on-site accommodation and facilities are identified.
  • 2.2. Site office, storage sheds and on-site toilet facilities are arranged, received and positioned.
  • 2.3. Site signage is erected to comply with regulations.
  • 2.4. Processes are developed and implemented to identify and protect existing services at the site.
  • 2.5. Council requirements are identified and met.
3. Organise the delivery of plant.
  • 3.1. On-site plant delivery dates are confirmed.
  • 3.2. Hoardings are erected and rubbish removal facilities are arranged.
4. Arrange the connection of temporary services.
  • 4.1. Temporary power and water connections are arranged with service providers.
  • 4.2. Temporary site access and egress are arranged and authorisations obtained from the local authority.
5. Organise on-site human resources.
  • 5.1. On-site human resource requirements are identified.
  • 5.2. Construction work supervisor is engaged or appointed.
  • 5.3. Industrial relations and safety matters occurring on supervised work site that could impact on the resourcing and preparation for building work are addressed where required.
  • 5.4. Appropriate personnel is engaged according to project needs.
6. Order materials.
  • 6.1. Orders for prefabricated materials are placed using approved company documentation and site delivery dates are confirmed.
  • 6.2. Construction arrangements required by contract are finalised to satisfy the project schedule.
RANGE STATEMENT
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Authorities include:
electricity authorities
environmental protection agencies
local government agencies
road traffic authorities
water authorities.
On-site accommodation and facilities include:
caravans
dormitories
lunch rooms
office facilities
sheds
toilet facilities.
Council requirements include:
consent matters
heritage protection
tree conservation.
Plant includes:
air compressors
pile driving equipment
portable generators and lighting equipment
pumps
wheeled or tracked earthmoving equipment.
On-site human resource requirements include:
administrative personnel
construction workers
cooks and kitchen hands
drivers and machine operators
supervisors and forepersons
tradespersons.
EVIDENCE GUIDE
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed by identifying, planning and putting in place the essential infrastructure (including human, physical, plans and processes) required to commence and support a construction project.
This unit of competency can be assessed in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person who demonstrates competency in this unit must be able to provide evidence of the ability to:
procure resources effectively
communicate effectively, both verbally and in writing with suppliers and subcontractors
complete documentation to organisational standards
advise appropriate authorities and gain necessary approvals or responses.
Context of and specific resources for assessment
This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints.
Assessment of essential underpinning knowledge will usually be conducted in an off-site context.
Assessment is to comply with relevant regulatory or Australian standards' requirements.
Resource implications for assessment include:
documentation that should normally be available in either a building or construction office
relevant codes, standards and government regulations
office equipment, including calculators, photocopiers and telephone systems
computers with appropriate software to view 2-D CAD drawings, run costing programs and print copies
a technical reference library with current publications on measurement, design, building construction and manufacturers' product literature
a suitable work area appropriate to the construction process.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Method of assessment
Assessment methods must:
satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package
include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
reinforce the integration of employability skills with workplace tasks and job roles
confirm that competency is verified and able to be transferred to other circumstances and environments.
Validity and sufficiency of evidence requires that:
competency will need to be demonstrated over a period of time reflecting the scope of the role and the practical requirements of the workplace
where the assessment is part of a structured learning experience the evidence collected must relate to a number of performances assessed at different points in time and separated by further learning and practice, with a decision on competency only taken at the point when the assessor has complete confidence in the person's demonstrated ability and applied knowledge
all assessment that is part of a structured learning experience must include a combination of direct, indirect and supplementary evidence.
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.
Replaces
State Code National Code Title Type
W5903 BCGBC4017A Arrange resources and prepare for the building or construction project Unit of competency
Replaced By
State Code National Code Title Type
OCR27 CPCCBC4017 Arrange resources and prepare for the building and construction project Unit of competency