Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Install pre-cast parapets
Install pre-cast parapets
Unit of competency
National Code
RIICBM303D
RIICBM303D
State Code
WH041
WH041
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
27/05/2014
Field of Education
030901 - Construction Engineering
Original Release Date
27/05/2014
Nominal Hours
68
Description
This unit describes a participant’s skills and knowledge required to install pre-cast parapets in Civil Construction.This unit is appropriate for those working in operational roles. Licensing, legislative, regulatory and certification requirements that apply to this unit can vary between states, territories, and Industry sectors. Relevant information must be sourced prior to application of the unit.
Notes
Elements and Performance Criteria
1. Plan and prepare
- 1.1 Access, interpret and apply documentation to install pre-cast parapets and ensure the work activity is compliant
- 1.2 Obtain, interpret, clarify and confirm and work instructions before proceeding
- 1.3 Confirm and apply environmental protection and safety requirements
- 1.4 Obtain, interpret and implement traffic management signage requirements
- 1.5 Select and check for faults plant, tools and equipment to carry out tasks
- 1.6 Identify, address and report environmental issues, potential hazards and risks
- 1.7 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
2. Confirm installation details
- 2.1 Measure stirrup spacing and compare with spacing of cast in ligatures and brackets to eliminate difficulties when positioning units
- 2.2 Determine individual pre-cast parapet unit location
- 2.3 Determine sequence of parapet installation and carry out
- 2.4 Check parapets for conformity to design prior to lifting
- 2.5 Check lifting points on pre-cast units for serviceability
3. Install pre-cast parapet units
- 3.1 Raise pre-cast parapet end unit to allow fitting of bracket
- 3.2 Manoeuvre pre-cast parapet unit into the vertical position
- 3.3 Guide pre-cast parapet unit into approximate position and attach locating bolts to cast in brackets
- 3.4 Correctly establish vertical and horizontal alignment of pre-cast parapet end units and tighten bolts
- 3.5 Install intermediate pre-cast parapet units in approximate positions
- 3.6 Check pre-cast end units for correct height and alignment
- 3.7 Adjust intermediate pre-cast parapet units to design alignment and tighten locating bolts
- 3.8 Install anchor cable and fix ends
4. Finish parapet
- 4.1 Install services and fittings as required
- 4.2 Fit joints with foam inserts and groat
- 4.3 Form up and prepare cast in-situ infills of the pre-cast units
- 4.4 Place concrete and finish
- 4.5 Dismantle formwork and remove from site
5. Clean up
- 5.1 Clear work area and dispose of or recycle materials
- 5.2 Clean, check, maintain and store plant, tools and equipment
No information
No information
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| OCX99 | RIICBM303E | Install pre-cast parapets | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BFA8 | RII30919 | Certificate III in Civil Construction | Qualification |
| AZB0 | RII30915 | Certificate III in Civil Construction | Qualification |