Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Set up and prepare for drilling operations

Set up and prepare for drilling operations

Unit of competency
National Code
RIINHB301D
State Code
WH470
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
2.00
Current Release Date
07/12/2014
State Implementation and Classification
Approved Date
29/05/2014
Field of Education
030303 - Mining Engineering
Original Release Date
29/05/2014
Nominal Hours
60
Description
This unit describes a participant’s skills and knowledge required to set up and prepare for drilling operations in Drilling. This unit is appropriate for those working in operational roles. No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1. Plan and prepare for drilling operations
  • 1.1 Access, interpret and apply drilling operations documentation, and ensure the work activity is compliant
  • 1.2 Obtain, read, interpret, clarify and confirm work requirements
  • 1.3 Identify and address potential risks, hazards and environmental issues and implement control measures
  • 1.4 Select and wear appropriate personal protective equipment appropriate for work activities
  • 1.5 Communicate and coordinate activities with others throughout the work activity
  • 1.6 Identify and determine location and nature of any installed services near or crossing the proposed drill plan
  • 1.7 Identify and obtain all necessary permits and consents
  • 1.8 Develop contingency plans for changes in geological conditions
  • 1.9 Obtain and interpret emergency procedures, and be prepared for fire/accident/emergency
2. Prepare to drill
  • 2.1 Check all required personnel, equipment and supplies are available
  • 2.2 Check equipment is in good operational condition, and address identified issues
  • 2.3 Erect or place safety barriers where needed
  • 2.4 Check all modes of communication
  • 2.5 Select suitable lay down areas for separate storage of chemicals and fuels or other incompatible items
  • 2.6 Select locations for ancillary equipment to provide maximum efficiency and minimal risk to personnel
3. Set up drill and equipment
  • 3.1 Carry out pre-start and start up procedures
  • 3.2 Ensure a solid foundation for the rig
  • 3.3 Interpret plans and position equipment accurately
  • 3.4 Stabilise drill
  • 3.5 Align and secure mast at correct angle
  • 3.6 Position ancillary equipment accurately
4. Diagnose problems
  • 4.1 Recognise symptoms of problem
  • 4.2 Identify and isolate causes and determine solution
  • 4.3 Implement solution if within scope of authority and competence
  • 4.4 Seek help if problem is too complex
  • 4.5 Implement solution as directed
No information
No information
Replaces
State Code National Code Title Type
WB173 RIINHB301A Set up and prepare for drilling operations Unit of competency
Replaced By
State Code National Code Title Type
OBW23 RIINHB301E Set up and prepare for drilling operations Unit of competency
State Code National Code Title Type
J633 RII31813 Certificate III in Drilling Operations Qualification
AZB1 RII31815 Certificate III in Drilling Operations Qualification