Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Manage project information and communication
Manage project information and communication
Unit of competency
National Code
BSBPMG516A
BSBPMG516A
State Code
WG103
WG103
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
28/05/2013
Field of Education
080315 - Project Management
Original Release Date
28/05/2013
Nominal Hours
40
Description
This unit describes the performance outcomes, skills and knowledge required to link people, ideas and information at all stages in the project life cycle. Project communication management ensures the timely and appropriate generation, collection, dissemination, storage and disposal of project information through formal structures and processes.
Notes
Elements and Performance Criteria
1. Plan information and communication processes
- 1.1 Identify, analyse and document information requirements, with input from stakeholders, as the basis for communication planning
- 1.2 Develop, within delegated authority, an agreed communication management plan to support the achievement of project objectives
- 1.3 Establish and maintain designated project-management information system to ensure the quality, validity, timeliness and integrity of information and communication
2. Implement project information and communication processes
- 2.1 Manage the generation, gathering, storage, retrieval, analysis and dissemination of information by project staff and stakeholders
- 2.2 Implement, modify, monitor and control designated information-validation processes to optimise quality and accuracy of data
- 2.3 Implement and maintain appropriate communication networks
- 2.4 Identify and resolve communication and information-management system issues
3. Assess information and communication outcomes
- 3.1 Finalise and archive records according to agreed project information ownership and control requirements
- 3.2 Review project outcomes to determine the effectiveness of management information and communication processes and procedures
- 3.3 Identify and document lessons learned and recommended improvements for application to future projects
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Delegated authority means that activities may:
be conducted routinely or as changing circumstances dictate
be done independently within broad guidance
involve consultation with other project members, teams and internal stakeholders
involve taking a lead role in a team where required
involve the selection, use and supervision of appropriate communication-management methods and tools
take into account internal organisational change and external environmental change.
Communication management plan may include:
communication strategy, including:
allocated responsibility
frequency
media used
type
objectives
organisational chart
organisational communication policy and procedures
responsibilities
stakeholder communication expectations
stakeholder segmentation against interests, power and influence
target audience
type of project reporting.
Project-management information system:
is a means of communicating knowledge about the project
provides a systematic approach to the storage, searching and retrieval of information relevant to the project
may include:
access authority levels
complex computer-based systems
data ownership considerations
modified systems to cater for unique project requirements
privacy considerations
simple manual systems.
Communication networks may include:
client organisation
community groups
end users
formal networks
informal networks
internet and intranet-based
lobby groups
organisation's communication networks
project governance bodies, including:
expert groups
project directorate
reference groups
steering committees
task teams
working groups
social media.
Delegated authority means that activities may:
be conducted routinely or as changing circumstances dictate
be done independently within broad guidance
involve consultation with other project members, teams and internal stakeholders
involve taking a lead role in a team where required
involve the selection, use and supervision of appropriate communication-management methods and tools
take into account internal organisational change and external environmental change.
Communication management plan may include:
communication strategy, including:
allocated responsibility
frequency
media used
type
objectives
organisational chart
organisational communication policy and procedures
responsibilities
stakeholder communication expectations
stakeholder segmentation against interests, power and influence
target audience
type of project reporting.
Project-management information system:
is a means of communicating knowledge about the project
provides a systematic approach to the storage, searching and retrieval of information relevant to the project
may include:
access authority levels
complex computer-based systems
data ownership considerations
modified systems to cater for unique project requirements
privacy considerations
simple manual systems.
Communication networks may include:
client organisation
community groups
end users
formal networks
informal networks
internet and intranet-based
lobby groups
organisation's communication networks
project governance bodies, including:
expert groups
project directorate
reference groups
steering committees
task teams
working groups
social media.
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the following is essential:
developing and implementing a range of project communication that facilitates effective outcomes for a project of sufficient complexity to demonstrate the full range of performance requirements
applying workplace-based project information system
developing a project communication plan.
Context of and specific resources for assessment
Assessment must ensure:
access to project communication and information management documentation
consideration of feedback from project team members and other stakeholders as to how effectively communication was managed.
Method of assessment
A range of assessment methods should be used to assess practical skill and knowledge. The following examples are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third-party workplace reports of on-the-job performance by the candidate
oral or written questioning to assess knowledge of strategies for managing project information and communication and their application to different situations
analysis of responses in addressing case studies and scenarios that present issues and problems in project communication management
observation of performance in role plays that demonstrate communication skills
evaluation of communication management plan
review of identification and reporting of problems in communication and information management system.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the following is essential:
developing and implementing a range of project communication that facilitates effective outcomes for a project of sufficient complexity to demonstrate the full range of performance requirements
applying workplace-based project information system
developing a project communication plan.
Context of and specific resources for assessment
Assessment must ensure:
access to project communication and information management documentation
consideration of feedback from project team members and other stakeholders as to how effectively communication was managed.
Method of assessment
A range of assessment methods should be used to assess practical skill and knowledge. The following examples are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third-party workplace reports of on-the-job performance by the candidate
oral or written questioning to assess knowledge of strategies for managing project information and communication and their application to different situations
analysis of responses in addressing case studies and scenarios that present issues and problems in project communication management
observation of performance in role plays that demonstrate communication skills
evaluation of communication management plan
review of identification and reporting of problems in communication and information management system.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended.
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| D0935 | BSBPMG507A | Manage project communications | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| AUL32 | BSBPMG516 | Manage project information and communication | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| J681 | RII50413 | Diploma of Civil Construction Management | Qualification |
| D170 | BSB50807 | Diploma of International Business | Qualification |
| J521 | BSB51413 | Diploma of Project Management | Qualification |