Unit of competency Outline

Date retreived
23/07/2026 12:40 AM AWST

Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Test and commission electronic electrical equipment

Test and commission electronic electrical equipment

Unit of competency
National Code
UEPMNT352
State Code
OAI05
TGA Status
Deleted
DTWD Status
Deleted
Current Release Number
1.00
Current Release Date
31/10/2018
State Implementation and Classification
Approved Date
15/05/2019
Field of Education
031317 - Electronic Equipment Servicing
Original Release Date
15/05/2019
Nominal Hours
36
Description
This unit involves the skills and knowledge required to conduct testing and commissioning of electronic electrical equipment.Commissioning and testing is the process of ensuring all systems and components of a power generation facility's electronic electrical equipment are meeting operational requirements.Competency in this unit requires the ability to plan work, test electronic electrical equipment wiring systems, testing electronic electrical equipment, commissioning electronic electrical equipment and to report on all completed work tasks. Individuals will, in general, work under supervision in an electrical, electronic and/or mechanical equipment repair workshop or on site. Power generation maintenance personnel are typically trained and authorised to receive permits to work. No licensing, legislative or certification requirements apply to this unit at the time of publication.Note: Workplace practiceThe application of the skills and knowledge described in this unit of competency may require a licence or training permit to practice in the workplace, where work is carried out on gas and electrical installations. Additional and/or other conditions may apply under state and territory legislative and regulatory licensing requirements.
Notes
Elements and Performance Criteria
1 Plan and prepare for work
  • 1.1 Requirements including scope of work and assigned roles are identified and confirmed with appropriate personnel or by site inspection, in accordance with workplace procedures
  • 1.2 Work, Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations, legislative requirements, industry standards, codes of practice, manufacturers’ specifications, environmental obligations and workplace procedures are reviewed in preparation for work
  • 1.3 Resources are obtained and inspected for compliance with job specification
  • 1.4 Relevant plans, drawings and manuals are selected and used, in accordance with workplace procedures
  • 1.5 Correct materials and components for work are obtained and inspected, in accordance with workplace procedures, for compliance with job specification
  • 1.6 Work is planned, sequenced and prioritised, in accordance with workplace procedures
  • 1.7 Potential hazards are identified, and risk control measures are selected and implemented, in accordance with workplace procedures
  • 1.8 Work area is prepared, in accordance with workplace procedures
2 Test electronic electricalwiring systems
  • 2.1 Isolations for work are confirmed, in accordance with workplace procedures
  • 2.2 Electronic electrical wiring systems are tested using appropriate plans, drawings and manuals, in accordance with workplace procedures
  • 2.3 Electronic electrical wiring systems, including enclosures and/or supports, are inspected, in accordance with workplace procedures, prior to testing to ensure absence of damage, defects or deterioration
  • 2.4 Fixed electronic electrical wiring is tested, as appropriate, and results are documented to confirm compliance with job specification
3 Test electronic electricalequipment
  • 3.1 Isolations are confirmed, in accordance with workplace procedures site requirements
  • 3.2 Electronic electrical equipment is tested using appropriate plans, drawings and manuals, in accordance with workplace procedures
  • 3.3 Test conditions are confirmed and equipment is inspected, in accordance with workplace procedures, to ensure absence of any damage, defects or deterioration
  • 3.4 Electronic electrical equipment is tested using appropriate testing techniques, in accordance with workplace procedures
  • 3.5 Electronic electrical equipment test results are documented to confirm compliance with job specification
4 Commission electronic electricalequipment
  • 4.1 Isolations are confirmed, where appropriate, in accordance with workplace procedures and site requirements
  • 4.2 Electronic electrical equipment is commissioned using appropriate plans, drawings and manuals, in accordance with workplace procedures
  • 4.3 Electronic electrical equipment is set up, in accordance with workplace procedures, operational requirements and manufacturers' specifications
  • 4.4 Testing and monitoring procedures are followed, and results are documented to ensure equipment operates within manufacturers' specifications
  • 4.5 Final inspection is carried out, in accordance with workplace procedures
5 Complete work
  • 5.1 Work is completed and appropriate personnel are notified, in accordance with workplace procedures
  • 5.2 Work area is cleared of waste, cleaned, restored and secured in accordance with workplace procedures
  • 5.3 Tools and equipment are cleaned, maintained and stored, in accordance with workplace procedures
  • 5.4 Work completion details are finalised, in accordance with workplace procedures