Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Plan electrotechnology projects

Plan electrotechnology projects

Unit of competency
National Code
UEECD0029
State Code
OBZ28
TGA Status
Current
DTWD Status
Approved
Current Release Number
1.00
Current Release Date
05/10/2020
State Implementation and Classification
Approved Date
12/07/2021
Field of Education
080315 - Project Management
Original Release Date
12/07/2021
Nominal Hours
54
Description
This unit involves the skills and knowledge required to plan an electrotechnology project.It includes determining, developing and obtaining approval for an electrotechnology project plan. It also includes establishing budgets, critical path analysis, developing workflow strategies and documenting the plan.No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Determine an electrotechnology project
  • 1.1 Work health and safety (WHS)/occupational health and safety (OHS) procedures for relevant work area are identified and applied
  • 1.2 Techniques for project planning are reviewed and adopted in accordance with workplace policies and procedures
  • 1.3 Scope of the project is determined from design brief, specifications and/or other relevant documentation and discussions with appropriate person/s
2 Develop project plan proposal
  • 2.1 Plant, material, labour and other cost estimations are sought and obtained from appropriate person/s in accordance with workplace policies and procedures
  • 2.2 Project budget is determined from plant, material labour and other cost estimations in accordance with workplace policies and procedures
  • 2.3 Critical path analysis is applied to developing workflow strategies
  • 2.4 Sources and availability of materials and human resources required for the project are determined in accordance with workplace policies and procedures
  • 2.5 Risk management strategies are identified, assessed and applied in the project plan
  • 2.6 Project plan is reviewed against all inputs and adjusted to rectify any anomalies
  • 2.7 Project plan proposal is documented in accordance with workplace procedures
3 Obtain approval for project plan
  • 3.1 Project plan is presented and discussed with appropriate person/s
  • 3.2 Alterations to the project plan resulting from presentation/discussion are negotiated with appropriate person/s in accordance with workplace policies and procedures
  • 3.3 Final project plan is documented and approval obtained from appropriate person/s