Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Start and run-up a hydro turbine

Start and run-up a hydro turbine

Unit of competency
National Code
UEPOPS444
State Code
OAG27
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
31/10/2018
State Implementation and Classification
Approved Date
15/05/2019
Field of Education
030717 - Plant And Machine Operations
Original Release Date
15/05/2019
Nominal Hours
54
Description
This unit involves the skills and knowledge required to conduct safe hydro turbine run-ups to a stable operating condition.Run up of a hydro turbine will involve the operator making a sequence of checks prior to and during start up. This ensures that loading the turbine is completed in a safe and consistent manner. Competency in this unit requires the ability plan and prepare hydro turbine, start and run-up hydro turbine, test and analyse hydro turbine system faults and complete documentation. Individuals will, in general, work under supervision, in a power generation facility as an operator.Power generation plant operators are typically trained and authorised to isolate, prepare plant and issue permits to work.No licensing, legislative or certification requirements apply to this unit at the time of publication.Note: Workplace practiceThe application of the skills and knowledge described in this unit may require a licence or training permit to practice in the workplace where work is carried out on gas and electrical installations. Additional conditions may apply under state and territory legislative and regulatory licensing requirements.
Notes
Elements and Performance Criteria
1 Plan and prepare work
  • 1.1 Safety issues are identified, in accordance with workplace procedures, Work Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations and legislative requirements
  • 1.2 Work requirements are identified from relevant personnel and documentation, in accordance with workplace procedures
  • 1.3 Preoperational checks are carried out on hydro turbine plant, in accordance with manufacturers' recommendations, workplace procedures and site requirements
  • 1.4 Turbine running up and loading schedule are ascertained from relevant documentation, in accordance with workplace procedures
2 Run-up hydro turbine
  • 2.1 Hydro turbine and alternator auxiliary systems are started up and hydro turbine is run up, in accordance with manufacturers' specifications and workplace procedures
  • 2.2 Hydro turbine is monitored and observed to detect deviations from normal run up operating conditions
  • 2.3 Corrective actions are taken to rectify hydro turbine abnormalities, in accordance with manufacturers' recommendations and workplace procedures
  • 2.4 Alternator is synchronised and connected to electrical system, in accordance with workplace procedures and manufacturers' recommendations
  • 2.5 Alternator is loaded, in accordance with workplace procedures, manufacturers' recommendations and regulators requirements
3 Test hydro turbineplant operation
  • 3.1 Tests are performed, in accordance with workplace procedures
  • 3.2 Power generation system and hydro turbine plant are observed for correct operational response, in accordance with workplace procedures
4 Analyseand reportsystem faults
  • 4.1 Causes of abnormal hydro turbine plant operating conditions are identified, in accordance with workplace procedures by analysing technical and operational information
  • 4.2 Corrective action is taken, in accordance with workplace procedures
5 Complete documentation
  • 5.1 Hydro turbine plant problems, movements and status are reported, in accordance with workplace procedures
  • 5.2 Documentation is updated, in accordance with workplace procedures
No information
No information
Replaces
State Code National Code Title Type
WE423 UEPOPS444A Start and Run-up a Hydro Turbine Unit of competency
Replaced By
State Code National Code Title Type
ODY02 UEPOPS139 Start and run up a hydro turbine Unit of competency