Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Conduct concrete road paver operations

Conduct concrete road paver operations

Unit of competency
National Code
RIICRC311E
State Code
OCX80
TGA Status
Current
DTWD Status
Approved
Current Release Number
1.00
Current Release Date
25/01/2021
State Implementation and Classification
Approved Date
18/06/2021
Field of Education
030717 - Plant And Machine Operations
Original Release Date
18/06/2021
Nominal Hours
60
Description
This unit describes the skills and knowledge required to conduct concrete road paver operations in civil construction, including setting up and operating concrete road pavers across different surface and material types.It applies to those working in operational roles. They generally work under minimal supervision to undertake a broad range of tasks in varied work contexts, using some discretion and judgement in selecting equipment, services or contingency measures.Licensing, legislative and certification requirements that apply to this unit can vary between states, territories and industry sectors. Users must check requirements with relevant body before applying the unit.
Notes
Elements and Performance Criteria
1. Plan and prepare to conduct concrete road paver operations
  • 1.1 Obtain, interpret, clarify and confirm work requirements
  • 1.2 Access, interpret and apply documentation required to conduct concrete road paver operations and confirm work activity is compliant
  • 1.3 Identify and address potential risks, hazards and environmental issues, and implement control measures
  • 1.4 Select and wear personal protective equipment according to site requirements
  • 1.5 Identify, obtain, confirm and implement signage requirements
  • 1.6 Select plant, tools and equipment required to carry out tasks and check for faults
  • 1.7 Identify specified pavement type according to job requirements
2. Set up concrete road paver
  • 2.1 Set up paver width and settings according to job requirements
  • 2.2 Establish work area according to paving drawings and survey markings
  • 2.3 Conduct pre-start and maintenance checks according to manufacturer specifications and site requirements
3. Operate concrete road paver
  • 3.1 Adjust sensors and controls as required while paving according to job requirements
  • 3.2 Use communication systems and hand signals according to site requirements
  • 3.3 Operate paver according to manufacturer specifications and job and site requirements
  • 3.4 Complete shut-down and park-up procedures according to manufacturer specifications and site requirements
  • 3.5 Complete required documentation according to site requirements and report issues to appropriate personnel
4. Conduct clean-up activities
  • 4.1 Conduct wash down procedures according to manufacturer specifications and site requirements
  • 4.2 Clean-up work area and dispose of or recycle materials according to site requirements
  • 4.3 Clean, check, maintain and store plant and tools according to manufacturer specifications and site requirements