Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Commission fire sprinkler systems

Commission fire sprinkler systems

Unit of competency
National Code
CPCPFS4027A
State Code
WI773
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
17/01/2014
State Implementation and Classification
Approved Date
20/06/2014
Field of Education
039905 - Fire Technology
Original Release Date
20/06/2014
Nominal Hours
55
Description
This unit of competency specifies the outcomes required to commission fire sprinkler systems. It covers preparing for the work, identifying and confirming system specifications and requirements, physically testing and commissioning systems, and finalising work processes, including completing records and documentation.
Notes
Elements and Performance Criteria
1 Prepare for commissioning fire sprinkler systems.
  • 1.1 Commissioning inspections and tests required to validate that fire sprinkler system performance meets design requirements are determined in consultation with approving authority.
  • 1.2 Documentation required for commissioning is obtained and reviewed.
  • 1.3 Tasks are planned according to industry, legislative and workplace requirements and sequenced in conjunction with others involved in or affected by the work.
  • 1.4 Tools, equipment and materials for commissioning are selected and checked for serviceability.
  • 1.5 Work area is prepared to support efficient commissioning process.
2 Confirm that installation of system components correspond to design requirements.
  • 2.1 Fire sprinkler system components and locations are identified on drawings and specifications.
  • 2.2 Building is inspected to confirm that locations of system components correspond to design requirements, or location anomalies are reported.
  • 2.3 Types of sprinkler heads are confirmed as compatible, or anomalies are reported.
  • 2.4 Spaces between sprinkler heads are confirmed as correct, or anomalies are reported.
  • 2.5 Pipework is inspected and confirmed as functional, or jointing and supporting defects are reported.
  • 2.6 Valves are inspected for different commissioning tests to confirm correct type, adequate labelling, and orientation in required position.
  • 2.7 Pressure gauge schedule, block plan and interface diagram are confirmed as corresponding to design requirements.
  • 2.8 Water supply components, including any installed pumpsets, are checked and verified against design requirements.
  • 2.9 Changes to the building or existing conditions that could affect component performance are identified.
3 Conduct pressure tests and restore system to normal pressure.
  • 3.1 Static air-pressure test is conducted to confirm integrity of the system, and results are recorded according to relevant standards and workplace requirements.
  • 3.2 High pressure hydraulic test is conducted to confirm integrity of the system, and results are recorded according to relevant standards and workplace requirements.
  • 3.3 Leaks are identified and reported.
  • 3.4 System is drained and re-charged at normal pressure according to relevant standards and workplace requirements.
4 Conduct functional tests.
  • 4.1 Water supply functional proving test is conducted, and results are recorded according to relevant standards.
  • 4.2 Functional tests of system components and interfaces are conducted, and results recorded according to relevant standards and design requirements.
  • 4.3 Tests are conducted according to environmental and sustainability requirements.
5 Finalise commissioning process.
  • 5.1 System functionality and compliance with design specifications are confirmed.
  • 5.2 Componentry is set to operational function and pipework is charged with water according to specifications.
  • 5.3 Tools, equipment and materials are checked and stored and work area is left in good order.
  • 5.4 Documentation is completed and processed according to workplace requirements.
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Fire sprinkler systems may include:
deluge
dry pipe
pre-action
storage sprinklers
wall wetting
water mist
wet pipe.
Approving authority may be:
client representative
council representative
fire brigade official
fire protection consultant engineer
insurance company representative
system designer.
Documentation may include:
as-installed drawings
design calculations
logbooks
operator manuals.
Industry, legislative and workplace requirements may include:
codes and standards
environmental and sustainability
licensing
quality assurance
workplace health and safety.
Tools and equipment may include:
digital tachometers
flow testing equipment
hand tools
laser levels
measuring devices
personal protective equipment
pressure gauges.
Fire sprinkler system components may include:
air compressors
alarm valves
ball valves
brackets
discharge nozzles
flow switches
pipework
pressure gauges
pressure reducing valves
pressure relief valves
pressure switches
pumpsets
solenoids
sprinkler heads
water supply valves.
Functional tests may include checking the effective operation of:
brigade booster connections
control and actuator mechanisms, such as:
pressure switches
flow switches
control valves, such as:
pressure reducing
pressure relief
tank inflow
interfaces to other systems, including:
booster pumps
building services
control indicating equipment (CIE)
control of booster pumpsets
fire detection
heating, ventilation and air conditioning (HVAC)
occupant warning systems
valve monitoring controls
remote water proving points
water supply components, such as tank infill and suction lines.
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed in the workplace or a close simulation of the workplace environment providing that simulated or project-based assessment techniques fully replicate plumbing and services workplace conditions, materials, activities, responsibilities and procedures.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person should demonstrate the ability to:
locate, interpret and apply relevant information, standards and specifications to testing and commissioning fire sprinkler systems
apply safety requirements throughout the work sequence, including the use of personal protective clothing and equipment
as a minimum, the ability to commission:
one wet system connected to fixed pumpsets
one wet system connected to town main supply
one pre-action fire sprinkler system
commissioning must ensure:
correct identification of location, design specification and details of proposed system
correct selection and use of appropriate processes, tools and equipment
completion of work to specification
compliance with regulations, standards and workplace quality procedures and processes
effective communication with others
safe work practices.
Context of and specific resources for assessment
Assessment of this unit:
must be in the context of the work environment
may be conducted in an off-site context, provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills
must meet relevant compliance requirements.
Resource implications for assessment include:
an induction procedure
realistic tasks or simulated tasks covering the minimum task requirements
relevant specifications and work instructions
tools and equipment appropriate to applying safe work practices
support materials appropriate to activity
workplace instructions relating to safe work practices and addressing hazards and emergencies
safety data sheets, job safety analyses and safe work method statements
research resources, including industry-related systems information.
Method of assessment
Assessment for this unit must verify the practical application of the required skills and knowledge, using one or more of the following methods:
direct observation of tasks in real or simulated work conditions
questioning to confirm the ability to identify and interpret the essential underpinning knowledge required for practical application.
Guidance information for assessment
This unit could be assessed on its own or in combination with other units relevant to the job function.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Assessment processes and techniques should, as far as is practical, take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Replaced By
State Code National Code Title Type
OCM84 CPCPFS4027 Commission fire sprinkler systems Unit of competency
State Code National Code Title Type
J497 CPC40912 Certificate IV in Plumbing and Services Qualification