Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Participate in nippling-up and pressure tests
Participate in nippling-up and pressure tests
Unit of competency
National Code
RIIOGD402E
RIIOGD402E
State Code
OBW56
OBW56
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
05/03/2021
Field of Education
030303 - Mining Engineering
Original Release Date
05/03/2021
Nominal Hours
20
Description
This unit describes the skills and knowledge required to participate in nippling-up and pressure tests in drilling.This unit applies to those working in assistant roles. They generally perform tasks involving a broad range of varied activities most of which are complex and non-routine and are responsible for the quantity and quality of the output of others.Licensing, legislative and certification requirements that apply to this unit can vary between states, territories, and industry sectors. Users must check requirements with relevant body before applying the unit.
Notes
Elements and Performance Criteria
1. Plan and prepare for nippling-up and pressure testing
- 1.1 Obtain, interpret and confirm work requirements
- 1.2 Access, interpret and apply documentation for participating in nippling-up and pressure testing and confirm work activity is compliant
- 1.3 Identify and minimise environmental issues and potential hazards, and assess and address risks within scope of own role and according to workplace procedures
- 1.4 Select and wear personal protective equipment required for work activities
- 1.5 Communicate with other personnel at site according to work requirements and confirm briefings and handover details are communicated and received
- 1.6 Check and adjust casing bowl and position level
- 1.7 Perform blow out prevention (BOP) test as per operator’s written instructions
- 1.8 Carry out rig-up to drill-out operations
- 1.9 Carry out pressure tests prior to drilling out and record results
2. Pressure testing during intermediate and/or main holes
- 2.1 Confirm pressure test program and timing
- 2.2 Check cup testers and plugs for sizing and integrity
- 2.3 Monitor and maintain stack within deviation limit
3. Conduct housekeeping activities
- 3.1 Clean, check, maintain and store plant, tools and equipment
- 3.2 Report issues identified with plant, tools and equipment
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| WH520 | RIIOGD402D | Participate in nippling-up and pressure test | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BFH8 | RII41120 | Certificate IV in Drilling Oil & Gas (Onshore) | Qualification |