Unit of competency Outline

Date retreived
22/07/2026 12:42 PM AWST

Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Start Up a Boiler Unit

Start Up a Boiler Unit

Unit of competency
National Code
UEPOPS409A
State Code
S5252
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
07/11/2006
State Implementation and Classification
Approved Date
07/05/2008
Field of Education
030717 - Plant And Machine Operations
Original Release Date
07/05/2008
Nominal Hours
70
Description
1)
This unit deals with the skills and knowledge required to establish combustion in a boiler through to a stage at which combustion support energy is no longer necessary.
Notes
Elements and Performance Criteria
1 Plan and prepare work
  • 1.1 Safety issues are identified to comply with enterprise/site requirements
  • 1.2 Work requirements are identified from relevant personnel and documentation
  • 1.3 Pre operational checks are carried out on plant according to manufacturer's recommendations and site requirements
  • 1.4 Where appropriate, the teams and individuals roles and responsibilities within the team are identified and, where required, assist in the provision of the on-the-job training
2 Operate plant
  • 2.1 Pre-light conditions are established in accordance with enterprise standards and site requirements
  • 2.2 Combustion is established and supported in accordance with enterprise, manufacturer's and site requirements. Combustion support fuel consumption is kept at minimum levels
  • 2.3 Fuel and air and feed flows are adjusted to achieve required steam conditions and demand , observing operating requirements
  • 2.4 Plant is operated within limits of plant design, enterprise or site requirements
  • 2.5 Plant is monitored and observed to detect deviations from required operating conditions
  • 2.6 Corrective actions are taken to rectify abnormalities in accordance with manufacturer's and enterprise/site procedures
3 Test plant operation
  • 3.1 Tests are performed in accordance with defined procedures applicable to the operational test
  • 3.2 System and plant is observed for correct operational response
  • 3.3 Corrective action is taken when response is not in accordance with documentation, plant integrity or personnel safety requirements
  • 3.4 Plant is returned to required operational status upon completion of test
4 Analyse system faults
  • 4.1 Causes of abnormal plant operating conditions are identified by analysing the technical and operational information in a logical and sequential manner
  • 4.2 Corrective action taken is in accordance with enterprise/site procedures
  • 4.3 Plant integrity and personnel safety is maintained through consultation with appropriate personnel, and reference to plant, technical and operational documentation
  • 4.4 Appropriate personnel are notified when defects are detected
5 Complete documentation
  • 5.1 Documentation is updated and plant problems, movements, abnormalities and status are reported and logged in accordance with enterprise/site procedures
No information
No information
Replaces
State Code National Code Title Type
M1649 UTPNEG206A Manage a boiler unit start up Unit of competency
Replaced By
State Code National Code Title Type
WE395 UEPOPS409B Start up a boiler unit Unit of competency
State Code National Code Title Type
S503 UEP40106 Certificate IV in ESI Generation (Systems Operations) Qualification