Unit of competency Outline

Date retreived
22/07/2026 10:23 PM AWST

Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Carry out mechanical general demolition

Carry out mechanical general demolition

Unit of competency
National Code
CPCCDE3011A
State Code
D7379
TGA Status
Deleted
DTWD Status
Deleted
Current Release Number
1.00
Current Release Date
19/05/2011
State Implementation and Classification
Approved Date
10/10/2011
Field of Education
030717 - Plant And Machine Operations
Original Release Date
10/10/2011
Nominal Hours
32
Description
This unit of competency specifies the outcomes required to demolish buildings, structures and ancillary components using mechanical demolition techniques.This unit includes the preparation of the site for the demolition process and the removal of materials and debris.
Notes
Elements and Performance Criteria
1. Plan and prepare.
  • 1.1. Work instructions and operational details are obtained using relevant information, confirmed and applied for planning and preparation purposes.
  • 1.2. Safety (OHS) requirements are followed in accordance with safety plans and policies.
  • 1.3. Signage and barricade requirements are identified and implemented.
  • 1.4. Plant and tools and equipment are selected to carry out tasks that are consistent with the requirements of the job, checked for serviceability and any faults are rectified or reported prior to commencement.
  • 1.5. Environmental requirements are identified for the project in accordance with environmental plans and regulatory obligations and applied.
2. Prepare demolition site.
  • 2.1. Requirements of site demolition plan are interpreted in accordance with workplace procedures.
  • 2.2. Structural engineering certificate for floor loadings is obtained and checked for plant and equipment use.
  • 2.3. Audit of property/dilapidation survey is conducted to determine condition of work site and surrounds prior to work commencing.
  • 2.4. Confirmation is obtained from supervisor and regulatory authorities that all existing services have been disconnected.
  • 2.5. Hazardous material is identified for separate handling in accordance with workplace requirements and instructions.
  • 2.6. Fall protection devices are installed and anchored/secured in accordance with workplace requirements.
  • 2.7. Mechanical equipment and plant are positioned in operating locations and appropriate exclusion zone and traffic control are arranged.
3. Demolish structure.
  • 3.1. Mechanical plant is operated in accordance with manufacturer specifications, standards and workplace procedures to carry out demolition process.
  • 3.2. Direction and assistance is provided to plant operators in accordance with workplace procedures during the demolition process.
  • 3.3. Measures are used to reduce dangerous and environmental hazards of fire, dust, noise and vibration in accordance with regulations, standards and workplace requirements.
4. Remove materials from site.
  • 4.1. Materials and debris are removed from demolition area according to demolition method statement and workplace procedures.
  • 4.2. Re-usable and recyclable materials are salvaged and stored in accordance with workplace procedures.
5. Clean up.
  • 5.1. Work area is cleared and materials disposed of, reused or recycled in accordance with legislation, regulations, codes of practice and job specification.
  • 5.2. Plant, tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and standard work practices.
RANGE STATEMENT
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Information includes:
diagrams or sketches
instructions issued by authorised organisational or external personnel
manufacturer specifications and instructions, where specified
MSDS
memos
regulatory and legislative requirements pertaining to the conduct of mechanical demolition processes
relevant Australian standards
safe work procedures relating to the conduct of mechanical demolition processes
signage
verbal, written and graphical instructions
work bulletins
work schedules, plans and specifications.
Planning and preparation include:
assessment of conditions and hazards
determination of work requirements and safety plans and policies
equipment defect identification
work site inspection.
Safety (OHS) is to be in accordance with state and territory legislation and regulations and project safety plan and may include:
emergency procedures, including extinguishing fires, organisational first aid requirements and evacuation
handling activities that may require the assistance of others or the use of manual or mechanical lifting devices where size, weight or other issues, such as a disability are a factor
hazard control
hazardous materials and substances, including asbestos, lead-based paints, dust, pesticide residue, animal residue and the safe handling or quarantining procedures for each
organisational first aid
PPE prescribed under legislation, regulations and workplace policies and practices
safe operating procedures, including the conduct of operational risk assessment and treatments associated with:
earth leakage boxes
falling objects
lighting
plant movement
power cables, including overhead service trays, cables and conduits
restricted access barriers
surrounding structures
traffic control
trip hazards
work site visitors and the public
working at heights
working in confined spaces
working in proximity to others
use of tools and equipment
workplace environmental requirements and safety.
Plant:
may be fitted with:
buckets, including 4 in 1 buckets
grabs
pulverisers
rippers
rock breakers
shears
may include:
vibrating plates.
Tools and equipment include:
angle grinders
barricades
bars (crow and pinch)
bolt cutters
brooms
compressors
concrete saws
electric testers
picks and mattocks
pneumatic picks and rock breakers
power drills and saws
quick cut saws
shovels and spades
signs
sledge hammers
wheelbarrows.
Environmental requirements include:
clean-up management
dust and noise
sedimentation control
vibration
waste management.
Audit:
is in accordance with:
site demolition plan, which documents the demolition process and safe work practices
may include:
assessment of condition of property and surrounds
communication with those who may be affected by the demolition task
determination of floor loadings
erection of scaffolding
identification of hazardous materials
identification of position of hoses and cables clear of hazards
installation of supports and bracing
location of signage and barricades
provision for site safety.
Services include:
computer and communication
electricity
gas
telephone
water.
Mechanical equipment and plant:
include excavators
may be performed by backhoes and skidsteer loaders.
Demolition may be performed:
on a new construction site or an existing structure being renovated or extended which involves the complete or partial removal of components.
EVIDENCE GUIDE
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person who demonstrates competency in this unit must be able to provide evidence of the ability to:
locate, interpret and apply relevant information, standards and specifications
comply with site safety plan and OHS legislation, regulations and codes of practice applicable to workplace operations
comply with organisational policies and procedures including quality requirements
safely and effectively operate and use tools, plant and equipment
communicate and work effectively and safely with others
as a minimum, given a site demolition plan and instructions, using an excavator and selected attachments, knock down a single storey building, relocating salvage on site for later removal and disposal of debris and waste, ensuring:
correct identification of requirement and conduct of the demolition
correct selection and use of appropriate processes, plant and equipment
completing all work to specification
compliance with regulations, standards and organisational quality procedures and processes.
Context of and specific resources for assessment
This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints.
Assessment of essential underpinning knowledge will usually be conducted in an off-site context.
Assessment is to comply with relevant regulatory or Australian standards' requirements.
Resource implications for assessment include:
an induction procedure and requirement
realistic tasks or simulated tasks covering the mandatory task requirements
relevant specifications and work instructions
tools and equipment appropriate to applying safe work practices
support materials appropriate to activity
workplace instructions relating to safe work practices and addressing hazards and emergencies
material safety data sheets
research resources, including industry related systems information.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Method of assessment
Assessment methods must:
satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package
include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
reinforce the integration of employability skills with workplace tasks and job roles
confirm that competency is verified and able to be transferred to other circumstances and environments.
Validity and sufficiency of evidence requires that:
competency will need to be demonstrated over a period of time reflecting the scope of the role and the practical requirements of the workplace
where the assessment is part of a structured learning experience the evidence collected must relate to a number of performances assessed at different points in time and separated by further learning and practice, with a decision on competency only taken at the point when the assessor has complete confidence in the person's demonstrated ability and applied knowledge
all assessment that is part of a structured learning experience must include a combination of direct, indirect and supplementary evidence.
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.
Replaces
State Code National Code Title Type
W9402 CPCCDE3001A Carry out mechanical general demolition Unit of competency
State Code National Code Title Type
D393 CPC30411 Certificate III in Demolition Qualification