Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Operate and monitor pipeline control systems
Operate and monitor pipeline control systems
Unit of competency
National Code
UEGNSG108
UEGNSG108
State Code
OAD19
OAD19
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
04/01/2019
Field of Education
040327 - Plumbing
Original Release Date
04/01/2019
Nominal Hours
54
Description
This unit involves the skills and knowledge required to operate and monitor pipeline system.It includes monitoring, operating and identifying faults on pipeline control system, compression systems, prime movers, instrument and control systems and valve systems, selecting and using relevant tools, equipment and testing devices to complete work and relevant documentation.No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Plan to operate and monitor pipeline control system
- 1.1 Work schedule, drawings, plans, job requirements, and material lists are obtained, analysed and confirmed by site inspection, as required, and work planned and coordinated in accordance with workplace and environmental procedures
- 1.2 Work is prioritised and sequenced for completion within acceptable timeframes following consultation with relevant person/s in accordance with workplace procedures
- 1.3 Hazards are identified, work health and safety (WHS)/occupational health and safety (OHS) risks are assessed and control measures prioritised, implemented and monitored in accordance with workplace procedures
- 1.4 Job requirements and workplace procedures for the work are obtained for work sites and communicated to relevant person/s in accordance with workplace procedures
- 1.5 WHS/OHS, environmental and sustainable energy policies and procedures related to the work are identified, obtained and applied to ensure safe systems of work are followed
- 1.6 Relevant work permit/s are obtained to coordinate and perform the work in accordance with regulatory and job requirements and workplace procedures
- 1.7 Person/s, equipment, tools and personal protective equipment (PPE) required for the job are identified, scheduled, obtained and checked for correct operation and safety in accordance with workplace procedures
- 1.8 Clients are provided with possible solutions and options within the scope, acceptable cost and job requirements parameters
- 1.9 Communication issues with relevant stakeholders are resolved and work coordinated in accordance with work schedule and workplace procedures
- 1.10 Person/s participating in work are briefed and responsibilities coordinated and authorised as required in accordance with workplace procedures
- 1.11 System status is confirmed through communication with pipeline control centre in accordance with workplace procedures
2 Operate and monitor pipelinecontrolsystem
- 2.1 WHS/OHS risk control measures and environmental procedures are followed in accordance with workplace procedures
- 2.2 Hazardous activities are conducted safely in accordance with regulatory requirements and workplace procedures
- 2.3 Equipment and systems are inspected, tested and faults identified in accordance with work schedule, job requirements and workplace procedures
- 2.4 Hazard warnings and safety signs are recognised, hazards and WHS/OHS risks assessed and reported to authorised person/s for directions in accordance with workplace procedures
- 2.5 Operating conditions and performance of equipment and systems are monitored through checking gauge levels, temperatures and flow indicators in accordance with manufacturer instructions and workplace procedures
- 2.6 Pipeline equipment and system performance information is monitored and reported to relevant person/s to ensure safe and efficient operation of the pipeline system in accordance with workplace procedures
- 2.7 Fault finding and troubleshooting techniques are applied to identify repairs or maintenance required in accordance with job requirements and workplace procedures
- 2.8 Work is coordinated to ensure completion in agreed timeframe and to industry standards with a minimum of waste in accordance with job requirements and workplace procedures
- 2.9 Unplanned situations are responded to in accordance with workplace procedures, in a manner that minimises risk to personnel and equipment
- 2.10 Quality and safety checks of work are conducted in accordance with job requirements, workplace procedures and industry standards
3 Complete work and relevant documentation
- 3.1 Work undertaken is checked against work schedule for conformance and anomalies and proposed solutions reported to relevant person/s in accordance with workplace and environmental procedures
- 3.2 Accidents and injuries are reported and followed up as required in accordance with workplace procedures
- 3.3 Work site is rehabilitated, cleaned up and confirmed safe in accordance with workplace procedures
- 3.4 Tools, equipment and any surplus resources and materials are cleaned, checked and returned to storage in accordance with workplace procedures
- 3.5 Relevant work permit/s is signed off in accordance with job requirements and workplace procedures
- 3.6 Work completion records, reports, documentation and as installed/modified drawing/s are completed, processed and the appropriate person/s notified in accordance with workplace procedures
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| S8137 | UEGNSG108B | Operate and monitor pipeline control systems | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| OEJ64 | UEGNSG064 | Operate and monitor pipeline control systems | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BDY6 | UEG40118 | Certificate IV in Gas Supply Industry Operations | Qualification |
| BHJ3 | UEG40221 | Certificate IV in Gas Supply Industry Operations | Qualification |
| BGL2 | UEG30120 | Certificate III in Gas Supply Industry Operations | Qualification |
| BHJ2 | UEG30121 | Certificate III in Gas Supply Industry Operations | Qualification |
| BGX6 | UEG50120 | Diploma of Gas Supply Industry Operations | Qualification |
| BGK8 | UEG40220 | Certificate IV in Gas Supply Industry Operations | Qualification |
| BDY4 | UEG60118 | Advanced Diploma of Gas Supply Industry Operations | Qualification |
| BDY5 | UEG50118 | Diploma of Gas Supply Industry Operations | Qualification |
| BDY3 | UEG30118 | Certificate III in Gas Supply Industry Operations | Qualification |
| BGK2 | UEG60120 | Advanced Diploma of Gas Supply Industry Operations | Qualification |