Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Shut down a hydro turbine

Shut down a hydro turbine

Unit of competency
National Code
UEPOPS445
State Code
OAG26
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
31/10/2018
State Implementation and Classification
Approved Date
15/05/2019
Field of Education
030717 - Plant And Machine Operations
Original Release Date
15/05/2019
Nominal Hours
54
Description
This unit involves the skills and knowledge required to conduct a shutdown of a hydro turbine to where it can be placed at rest safely.Shutdown of a hydro turbine will involve the operator making a sequence of checks prior to and during shutdown. This ensures that the shutdown of the turbine is completed in a safe and consistent manner.Competency in this unit requires the ability plan and prepare hydro turbine shut down, conduct a shutdown, test hydro turbine plant operation during shut down, analyse hydro turbine system faults during shutdown and complete documentation. Individuals will, in general, work under supervision, in a power generation facility as an operator.Power generation plant operators are typically trained and authorised to isolate, prepare plant and issue permits to work.No licensing, legislative or certification requirements apply to this unit at the time of publication.Note: Workplace practiceThe application of the skills and knowledge described in this unit may require a licence or training permit to practice in the workplace where work is carried out on gas and electrical installations. Additional conditions may apply under state and territory legislative and regulatory licensing requirements.
Notes
Elements and Performance Criteria
1 Plan and preparework
  • 1.1 Safety issues are identified, in accordance with workplace procedures and Work, Health and Safety (WHS)/Occupational Health and Safety (OHS) regulations
  • 1.2 Work requirements are identified from appropriate personnel and documentation, in accordance with workplace procedures
  • 1.3 Hydro turbine running up and loading schedule are ascertained from documentation, in accordance with workplace procedures
2 Conduct hydro turbineshut down
  • 2.1 Hydro turbine load is reduced, in accordance with workplace procedures and manufacturers' recommendations
  • 2.2 Hydro turbine and alternator are removed from the system, in accordance with workplace and manufacturers' operating procedures
3 Test hydro turbineplant operationduring shut down
  • 3.1 Tests are performed, in accordance with workplace procedures
  • 3.2 Power generation system and hydro turbine plant are observed, in accordance with workplace procedures for correct operational response
4 Analyse system faultsduring hydro turbine shut down
  • 4.1 Causes of abnormal hydro turbine plant operating conditions are identified, in accordance with workplace procedures, and by analysing technical and operational information
  • 4.2 Corrective action is taken, is in accordance with workplace procedures
5 Complete documentation
  • 5.1 Hydro turbine plant problems, movements and status are reported, in accordance with workplace procedures
  • 5.2 Documentation is updated, in accordance with workplace procedures
No information
No information
Replaces
State Code National Code Title Type
WE424 UEPOPS445A Shut Down a Hydro Turbine Unit of competency
Replaced By
State Code National Code Title Type
ODY06 UEPOPS136 Shut down a hydro turbine Unit of competency