Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Finish concrete

Finish concrete

Unit of competency
National Code
CPCCCO3022A
State Code
D7360
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
19/05/2011
State Implementation and Classification
Approved Date
10/10/2011
Field of Education
040399 - Building, N.e.c.
Original Release Date
10/10/2011
Nominal Hours
100
Description
This unit of competency specifies the outcomes required to finish concrete surfaces that have been placed and screeded in domestic, commercial and civil applications to provide a finish for designated requirements.The unit includes both manual and mechanical finishing techniques.
Notes
Elements and Performance Criteria
1. Plan and prepare.
  • 1.1. Work instructions and operational details are obtained using relevant information, confirmed and applied for planning and preparation purposes.
  • 1.2. Safety (OHS) requirements are followed in accordance with safety plans and policies.
  • 1.3. Signage and barricade requirements are identified and implemented.
  • 1.4. Plant, tools and equipment selected to carry out tasks are consistent with the requirements of the job, checked for serviceability and any faults are rectified or reported prior to commencement.
  • 1.5. Materials quantity requirements are calculated in accordance with plans, specifications and quality requirements.
  • 1.6. Materials appropriate to the work application are identified, obtained, prepared, safely handled and located ready for use.
  • 1.7. Environmental requirements are identified for the project in accordance with environmental plans and regulatory obligations and applied.
2. Finish concrete.
  • 2.1. Float and trowel are applied after initial screeding to assist in maintaining a level surface and to remove screeding inaccuracies.
  • 2.2. Mechanical trowelling is applied to consolidate and densify the setting concrete surface.
  • 2.3. Control joints are installed, edges finished and concrete trowelled to specifications.
  • 2.4. Final trowel/ finish is applied to concrete surface to specifications.
3. Clean up.
  • 3.1. Work area is cleared and materials disposed of, reused or recycled in accordance with legislation, regulations, codes of practice and job specification.
  • 3.2. Plant, tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and standard work practices.
RANGE STATEMENT
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Information includes:
diagrams or sketches
instructions issued by authorised organisational or external personnel
manufacturer specifications and instructions, where specified
MSDS
memos
regulatory and legislative requirements pertaining to finishing concrete
relevant Australian standards
safe work procedures relating to finishing concrete
signage
verbal, written and graphical instructions
work bulletins
work schedules, plans and specifications.
Planning and preparation include:
assessment of conditions and hazards
determination of work requirements and safety plans and policies
equipment defect identification
work site inspection.
Safety (OHS) is to be in accordance with state and territory legislation and regulations and project safety plan and may include:
emergency procedures, including extinguishing fires, organisational first aid requirements and evacuation
handling activities that may require the assistance of others or the use of manual or mechanical lifting devices where size, weight or other issues, such as a disability are a factor
hazard control
hazardous materials and substances
organisational first aid
PPE prescribed under legislation, regulations and workplace policies and practices
safe operating procedures, including the conduct of operational risk assessment and treatments associated with:
earth leakage boxes
lighting
power cables, including overhead service trays, cables and conduits
restricted access barriers
surrounding structures
traffic control
trip hazards
work site visitors and the public
working at heights
working in confined spaces
working in proximity to others
use of firefighting equipment
use of tools and equipment
workplace environmental requirements and safety.
Tools and equipment:
include:
bull floats
magnesium trowels
power trowels
steel trowels
wooden floats
may include:
brooms
channel trowels
edging tools
hoses
kerb
step readers
stipple plates.
Quality requirements include:
internal company quality policy and standards
manufacturer specifications where specified
relevant regulations, including Australian standards
workplace operations and procedures.
Materials include:
concrete
water.
Environmental requirements include:
clean-up management
dust and noise
stormwater management
vibration
waste management.
Level surface:
is a concrete surface that has been placed and screeded to the reduced level (RL) in accordance with drawings and specifications.
Assistance in maintaining a level surface includes:
assessing the curing process to allow manual and mechanical trowelling to be applied.
Control joints:
are included in the concrete surface to control cracking.
Finishing techniques include:
broom finished
brushed
bull float
hand float (wooden, magnesium or composition)
mechanical trowelling machine
slip resistance
spraying and brushing to expose aggregate
steel trowel
to engineer's drawings and specifications
wood float.
Edge finishing types include:
fine
rounded
straight edge.
EVIDENCE GUIDE
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person who demonstrates competency in this unit must be able to provide evidence of the ability to:
locate, interpret and apply relevant information, standards and specifications
comply with site safety plan and OHS legislation, regulations and codes of practice applicable to workplace operations
comply with organisational policies and procedures including quality requirements
safely and effectively operate and use tools, plant and equipment
communicate and work effectively and safely with others
using a hand trowel and power trowel finish, a minimum of 100 square metres of concrete slab to job specifications.
Context of and specific resources for assessment
This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints.
Assessment of essential underpinning knowledge will usually be conducted in an off-site context.
Assessment is to comply with relevant regulatory or Australian standards' requirements.
Resource implications for assessment include:
an induction procedure and requirement
realistic tasks or simulated tasks covering the mandatory task requirements
relevant specifications and work instructions
tools and equipment appropriate to applying safe work practices
support materials appropriate to activity
workplace instructions relating to safe work practices and addressing hazards and emergencies
material safety data sheets
research resources, including industry related systems information.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Method of assessment
Assessment methods must:
satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package
include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
reinforce the integration of employability skills with workplace tasks and job roles
confirm that competency is verified and able to be transferred to other circumstances and environments.
Validity and sufficiency of evidence requires that:
competency will need to be demonstrated over a period of time reflecting the scope of the role and the practical requirements of the workplace
where the assessment is part of a structured learning experience the evidence collected must relate to a number of performances assessed at different points in time and separated by further learning and practice, with a decision on competency only taken at the point when the assessor has complete confidence in the person's demonstrated ability and applied knowledge
all assessment that is part of a structured learning experience must include a combination of direct, indirect and supplementary evidence.
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.
Replaces
State Code National Code Title Type
W9387 CPCCCO3002A Finish concrete Unit of competency
Replaced By
State Code National Code Title Type
WI728 CPCCCO3042A Finish concrete Unit of competency
State Code National Code Title Type
D392 CPC30311 Certificate III in Concreting Qualification