Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Prepare design of sprayed seal surfacing
Prepare design of sprayed seal surfacing
Unit of competency
National Code
RIICWD524B
RIICWD524B
State Code
WC344
WC344
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
04/11/2013
Field of Education
040103 - Urban Design And Regional Planning
Original Release Date
04/11/2013
Nominal Hours
60
Description
This unit covers the completion of and documentation of sprayed seal surfacing design in Civil Construction. It includes the preparation and planning for the design, undertaking of the design, finalisation of the design processes and supporting the application of the design.
Notes
Elements and Performance Criteria
1. Plan for the design of sprayed seal surfacing
- 1.1. Access, interpret and apply compliance documentation relevant to the work activity
- 1.2. Identify and confirm the sprayed seal surfacing project requirements and information for the completion of the design
- 1.3. Prepare a design plan which makes best use of the available resources and meets the design requirement
2. Undertake the design of sprayed seal surfacing
- 2.1. Interpret and analyse the relevant data and identify the available viable options for the design of sprayed seal surfacing
- 2.2. Interpret and analyse relevant data and recommend the preferred option that best meets the required project outcomes
- 2.3. Complete the design of the sprayed seal surfacing that safely, effectively and efficiently meets the required project outcomes
- 2.4. Prepare a cost estimate of the execution of the designed sprayed seal surfacing
- 2.5. Participate in the review of the sprayed seal surfacing design
- 2.6. Complete the documentation of the sprayed seal surfacing design
- 2.7. Monitor and coordinate the progress of other team members involved in the design process
- 2.8. Gain design approval
3. Finalise design processes of sprayed seal surfacing
- 3.1. Ensure filing of design records is completed
- 3.2. Complete and submit design cost and other reporting
- 3.3. Participate in performance review of the design process
- 3.4. Seek client feedback and contribute to the verification of the design
- 3.5. Close out all systems
4. Support and review the application of the design of sprayed seal surfacing
- 4.1. Provide clarification and advice to those applying the design
- 4.2. Review the application of the design and recommend changes for the continuous improvements of sprayed seal surfacing designs
- 4.3. Contribute to the validation of the design
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Relevant compliance documentation
may include:
legislative, organisational and site requirements and procedures
manufacturer's guidelines and specifications
Australian standards
code of practice
Employment and workplace relations legislation
Equal Employment Opportunity and Disability Discrimination legislation
Confirm
may include:
consultation with the client
consultation with others within the organisation
consultation with relevant authorities
conducting a risk assessment of the existing and potential hazards
obtaining further site data, including:
known and potential hazards, constraints and conditions
cultural and heritage data
traffic data
surface texture and condition of existing pavements
pavement geometry
geological data
geotechnical data
hydrological data
survey data
meteorological data
Sprayed seal surfacing
may include:
bitumen, including multigrade bitumen
polymer modified binders
bituminous emulsions
various aggregate sizes
Sprayed seal surfacing application may include:
new installations and maintenance of existing pavements
urban and rural roads
bridges
car parks
industrial hardstands
airfields
recreational facilities
urban and rural pathways
Project requirements and information
may include:
project specifications
contractual requirements
client's requirements
project site geological data
project site hydrological data
project site engineering survey data
project site cultural and heritage constraints
existing project design and drawings
Australian or other relevant standards
Design plan
may include:
human resource requirements
design hardware and software
coordination requirements
scheduling
review requirements
design process communication and reporting requirements
Preferred option factors
may include:
cost
site constraints
available resources
risk assessment of:
the existing conditions
the application of the design
maintainability of the completed works
Detailed design
may include:
calculations, including:
pavement loading
pavement stresses
traffic volumes
construction materials and services quantities
construction cost estimates
drawings
risk assessment of:
the existing conditions
the application of the design
maintainability of the completed works
health, safety and environmental requirements
contribution to ancillary documentation, which may include:
design notes
construction notes
supplementary drawings
input to the specifications
Relevant compliance documentation
may include:
legislative, organisational and site requirements and procedures
manufacturer's guidelines and specifications
Australian standards
code of practice
Employment and workplace relations legislation
Equal Employment Opportunity and Disability Discrimination legislation
Confirm
may include:
consultation with the client
consultation with others within the organisation
consultation with relevant authorities
conducting a risk assessment of the existing and potential hazards
obtaining further site data, including:
known and potential hazards, constraints and conditions
cultural and heritage data
traffic data
surface texture and condition of existing pavements
pavement geometry
geological data
geotechnical data
hydrological data
survey data
meteorological data
Sprayed seal surfacing
may include:
bitumen, including multigrade bitumen
polymer modified binders
bituminous emulsions
various aggregate sizes
Sprayed seal surfacing application may include:
new installations and maintenance of existing pavements
urban and rural roads
bridges
car parks
industrial hardstands
airfields
recreational facilities
urban and rural pathways
Project requirements and information
may include:
project specifications
contractual requirements
client's requirements
project site geological data
project site hydrological data
project site engineering survey data
project site cultural and heritage constraints
existing project design and drawings
Australian or other relevant standards
Design plan
may include:
human resource requirements
design hardware and software
coordination requirements
scheduling
review requirements
design process communication and reporting requirements
Preferred option factors
may include:
cost
site constraints
available resources
risk assessment of:
the existing conditions
the application of the design
maintainability of the completed works
Detailed design
may include:
calculations, including:
pavement loading
pavement stresses
traffic volumes
construction materials and services quantities
construction cost estimates
drawings
risk assessment of:
the existing conditions
the application of the design
maintainability of the completed works
health, safety and environmental requirements
contribution to ancillary documentation, which may include:
design notes
construction notes
supplementary drawings
input to the specifications
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:
knowledge of the requirements, procedures and instructions for the completion of and documentation of sprayed seal surfacing design
implementation of procedures and techniques for the safe, effective and efficient completion of and documentation of sprayed seal surfacing design
the identification of the relevant information and scope of the work required to meet the required outcomes
the identification of viable options and the selection of sprayed seal surfacing design that best meet the required outcomes
working with others to undertake and complete the documentation of sprayed seal surfacing design
consistent successful completion of and documentation of sprayed seal surfacing design
Context of and specific resources for assessment
This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.
The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.
Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.
Aboriginal people and other people from a non English speaking background may have second language issues.
Assessment of this competency requires typical resources normally used in a civil works environment. Selection and use of resources for particular worksites may differ due to site circumstances.
Where applicable, physical resources should include equipment modified for people with disabilities.
Access must be provided to appropriate learning and/or assessment support when required.
Method of assessment
This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:
written and/or oral assessment of the candidate's required knowledge to apply in undertaking of the completion of and documentation of sprayed seal surfacing design
observed, documented and/or first hand testimonial evidence of the candidate's:
implementation of appropriate procedures and techniques for the safe, effective and efficient achievement of the required outcomes
identification of the relevant information and scope of the work required to meet the required outcomes
identification of viable options and the selection of sprayed seal surfacing design that best meet the required outcomes
consistently achieving the required outcomes
first hand testimonial and documentary evidence of the candidate's:
working with others to undertake and complete the documentation of sprayed seal surfacing design
provision of clear and timely required support and advice on the completion of and documentation of sprayed seal surfacing design
Guidance information for assessment
Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
The evidence required to demonstrate competency in this unit must be relevant to worksite operations and satisfy all of the requirements of the performance criteria, required skills and knowledge and the range statement of this unit and include evidence of the following:
knowledge of the requirements, procedures and instructions for the completion of and documentation of sprayed seal surfacing design
implementation of procedures and techniques for the safe, effective and efficient completion of and documentation of sprayed seal surfacing design
the identification of the relevant information and scope of the work required to meet the required outcomes
the identification of viable options and the selection of sprayed seal surfacing design that best meet the required outcomes
working with others to undertake and complete the documentation of sprayed seal surfacing design
consistent successful completion of and documentation of sprayed seal surfacing design
Context of and specific resources for assessment
This unit must be assessed in the context of the work environment. Where personal safety or environmental damage are limiting factors, assessment may occur in a simulated environment provided it is realistic and sufficiently rigorous to cover all aspects of workplace performance, including task skills, task management skills, contingency management skills and job role environment skills.
The assessment environment should not disadvantage the participant. For example, language, literacy and numeracy demands of assessment should not be greater than those required on the job.
Customisation of assessment and delivery environment to sensitively accommodate cultural diversity.
Aboriginal people and other people from a non English speaking background may have second language issues.
Assessment of this competency requires typical resources normally used in a civil works environment. Selection and use of resources for particular worksites may differ due to site circumstances.
Where applicable, physical resources should include equipment modified for people with disabilities.
Access must be provided to appropriate learning and/or assessment support when required.
Method of assessment
This unit may be assessed in a holistic way with other units of competency. The assessment strategy for this unit must verify required knowledge and skill and practical application using more than one of the following assessment methods:
written and/or oral assessment of the candidate's required knowledge to apply in undertaking of the completion of and documentation of sprayed seal surfacing design
observed, documented and/or first hand testimonial evidence of the candidate's:
implementation of appropriate procedures and techniques for the safe, effective and efficient achievement of the required outcomes
identification of the relevant information and scope of the work required to meet the required outcomes
identification of viable options and the selection of sprayed seal surfacing design that best meet the required outcomes
consistently achieving the required outcomes
first hand testimonial and documentary evidence of the candidate's:
working with others to undertake and complete the documentation of sprayed seal surfacing design
provision of clear and timely required support and advice on the completion of and documentation of sprayed seal surfacing design
Guidance information for assessment
Consult the SkillsDMC User Guide for further information on assessment including access and equity issues.
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| WH216 | RIICWD524D | Prepare design of spray seal surfacing | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| W693 | RII40809 | Certificate IV in Civil Construction Design | Qualification |