Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Carry out load slinging of off-site materials
Carry out load slinging of off-site materials
Unit of competency
National Code
CPCCST2005
CPCCST2005
State Code
OCP59
OCP59
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
01/06/2021
Field of Education
030717 - Plant And Machine Operations
Original Release Date
01/06/2021
Nominal Hours
4
Description
This unit specifies the skills and knowledge required to sling and move materials under supervision. It includes selecting and securing slings and safely moving loads.Shifting equipment refers to equipment excluding that requiring a certificate of competency for operation as specified by state and territory licensing requirements.This unit is suitable for people with basic skills and knowledge who undertake routine work tasks under the direction of more experienced workers.Completion of the general construction induction training program specified by the model Code of Practice for Construction Work is required for any person who is to carry out construction work. Achievement of CPCWHS1001Prepare to work safely in the construction industrymeets this requirement. No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Plan and prepare.
- 1.1 Obtain and follow work instructions and workplace safety requirements.
- 1.2 Identify potential hazards and implement control measures.
- 1.3 Erect signage and barricades to create an exclusion zone.
- 1.4 Select tools for the task and check tool for serviceability and faults.
- 1.5 Calculate material weight to comply with safe working limits of slings and lifting equipment.
- 1.6 Identify and apply environmental requirements.
- 1.7 Select and check communication equipment suitable for the task.
2 Move, locate and secure load
- 2.1 Select, fit correctly and use personal protective equipment (PPE) appropriate for job.
- 2.2 Prepare materials for work application for load slinging.
- 2.3 Identify and locate shifting/anchorage points and select slings, tackles and associated shifting gear appropriate for the weight and shape of the load.
- 2.4 Inspect slings, tackles and lifting gear for wear and tear and damage and report faults to supervisor.
- 2.5 Position and securely attach strongbacks/stiffeners.
- 2.6 Secure packaging to protect load and connect load to lifting gear.
- 2.7 Prepare location to receive load.
- 2.8 Stand load vertically, if necessary, move to required location and secure in position.
- 2.9 Remove slings from load and lifting equipment and remove packaging from material.
3 Clean up.
- 3.1 Clean slinging equipment and check for and report damage.
- 3.2 Clear the work area, and dispose of, reuse or recycle materials following workplace and environmental requirements.
- 3.3 Complete necessary documentation.
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| W9555 | CPCCST2005A | Carry out load slinging of off-site materials | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BGB4 | CPC20720 | Certificate II in Drainage | Qualification |
| BGC1 | CPC32820 | Certificate III in Fire Protection | Qualification |
| BGB7 | CPC32720 | Certificate III in Gas Fitting | Qualification |
| BGD0 | CPC32620 | Certificate III in Roof Plumbing | Qualification |
| BGE7 | CPC32320 | Certificate III in Stonemasonry | Qualification |