Unit of competency Outline

Date retreived
22/07/2026 3:13 PM AWST

Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Splice and terminate optical fibre cable for telecommunications projects

Splice and terminate optical fibre cable for telecommunications projects

Unit of competency
National Code
ICTCBL330
State Code
OBA58
TGA Status
Current
DTWD Status
Approved
Current Release Number
1.00
Current Release Date
30/08/2019
State Implementation and Classification
Approved Date
27/11/2019
Field of Education
031309 - Communications Equipment Installation And Maintenance
Original Release Date
27/11/2019
Nominal Hours
35
Description
This unit describes the skills and knowledge required to splice and terminate optical fibre cable within an optical telecommunications transmission environment for new installations or upgrades of an optical backbone or access network, to achieve greater bandwidth and capacity required by emerging technology convergence for next generation networks (NGNs).It applies to technical staff who splice and terminate optical fibre cable for telecommunications projects for commercial or industrial fibre to the premises (FTTP) non-mechanical splicing installations.Licensing, legislative, regulatory and certification requirements apply to telecommunications systems. All customer cabling work in the telecommunications, fire, security and data industries must be performed by a registered cabler. All cablers are required to register with an Australian Communications and Media Authority (ACMA) accredited registrar. Cablers working with live optical fibre must obtain enterprise certification before commencing splicing work.
Notes
Elements and Performance Criteria
1. Prepare for splicing
  • 1.1 Select safety equipment to protect self and public according to industry guidelines and work health and safety (WHS) practices
  • 1.2 Confirm layout of installation according to physical conditions at site and relevant legislation, regulations, codes and standards
  • 1.3 Inform appropriate personnel of identified worksite hazards
  • 1.4 Locate other services from relevant authorities according to industry guidelines and safe practices
  • 1.5 Test for dangerous gases and place guards around open manholes according to WHS and environmental requirements
  • 1.6 Obtain approval for alterations to design according to industry guidelines
2. Check existing optical fibre cable
  • 2.1 Verify that cable is installed according to installation plan
  • 2.2 Visually inspect cable for signs of sheath damage and seek instructions from service provider when damage is identified
  • 2.2 Maintain minimum bend ratios according to manufacturer specifications to prevent cable damage and signal degradation
  • 2.3 Secure cable according to safe industry practice to avoid cable and sheath damage
3. Splice optical fibre cable
  • 3.1 Maintain safe work practices when using equipment to identify and verify fibre is not live before commencing splicing
  • 3.2 Seek instructions from service provider where fibre is live and, on receipt of required enterprise certification, follow service provider instructions accordingly
  • 3.3 Prepare cable end to expose optical fibres according to splicing method and manufacturer specifications
  • 3.4 Prepare and splice fibres using safe industry practice according to industry specifications
  • 3.5 Install and clean optical connectors with recommended cleaning material and re-inspect
  • 3.6 Test completed links for proof of performance according to industry standards
4. Terminate optical fibre cable
  • 4.1 Select connector unit to suit terminating frame according to design specifications
  • 4.2 Terminate cable according to design method and manufacturer specifications
  • 4.3 Test termination for transmission loss and light levels, and re-terminate if transmission loss exceeds industry standard
  • 4.4 Install protection devices on connectors to protect from exposure and contaminants
  • 4.5 Label and lay up cables in enclosure according to manufacturer instructions and industry guidelines
5. Finish job and report
  • 5.1 Remove waste and reinstate site according to industry guidelines
  • 5.2 Prepare reports, including test results and alterations to plans, according to telecommunications industry or enterprise policies
  • 5.3 Notify appropriate personnel of work completion and obtain sign-off
No information
No information
Replaces
State Code National Code Title Type
AWE93 ICTCBL208 Splice and terminate optical fibre cable for carriers and service providers Unit of competency