Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Maintain rail joints
Maintain rail joints
Unit of competency
National Code
TLIB2121
TLIB2121
State Code
AVK67
AVK67
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
23/02/2016
Field of Education
039907 - Rail Operations
Original Release Date
23/02/2016
Nominal Hours
20
Description
This unit involves the skills and knowledge required to maintain rail joints in accordance with rail industry standards, safeworking and regulatory requirements, and workplace procedures.It includes identifying and determining parameters or components that require repair, cutting and boring rail, maintaining rail joints and completing required documentation.People achieving competence in this unit will need to fulfil applicable state/territory legislated rail safety requirements and to comply with relevant codes of practice and/or guidelines.Work is performed under minimal supervision, generally in a team environment. It involves the application of routine operational principles and procedures when maintaining rail joints, as part of workplace activities across a variety of operational contexts within the Australian rail system.Operators of mechanised equipment must have undertaken training and, where appropriate, hold the relevant licence, permit or certificate and be recognised as competent for the class of machinery being used.No licensing, legislative or certification requirements apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1 Determine parameters or components that require adjustment
- 1.1 Rail joint condition, component, fastening and anchoring defects affecting rail joints are identified in accordance with organisational procedures
- 1.2 Hazards are identified, risks are assessed and control measures are implemented
- 1.3 Appropriate repair method is selected to ensure rail joint meets specifications
- 1.4 Scope of work is determined and resources are arranged
2 Check and maintain rail joint
- 2.1 Surfaces and component parts are checked in accordance with specifications and organisational procedures
- 2.2 Rail joint is maintained to specifications in accordance with organisational procedures
3 Complete documentation
- 3.1 Required documentation procedures and processes are confirmed
- 3.2 Documentation is filled in legibly and proofread
- 3.3 Documentation is processed in accordance with workplace procedures
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| WG253 | TLIB2121B | Maintain rail joints | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BGM7 | TLI27120 | Certificate II in Rail Infrastructure | Qualification |
| AWT3 | TLI21315 | Certificate II in Rail Infrastructure | Qualification |
| BHH8 | TLI27121 | Certificate II in Rail Infrastructure | Qualification |