Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Flash penetrations through roofs and walls

Flash penetrations through roofs and walls

Unit of competency
National Code
CPCPCM3021A
State Code
WF844
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
07/02/2013
State Implementation and Classification
Approved Date
20/06/2014
Field of Education
040327 - Plumbing
Original Release Date
20/06/2014
Nominal Hours
30
Description
This unit of competency specifies the outcomes required to set out, cut and flash a roof and wall penetration.
Notes
Elements and Performance Criteria
1 Prepare for work.
  • 1.1 Plans and specifications are obtained from job supervisor and site inspection.
  • 1.2 Work health and safety (WHS) and environmental requirements associated with the flashing of penetrations through roofs and walls are adhered to throughout the work.
  • 1.3 Quality assurance requirements are identified and adhered to according to workplace requirements.
  • 1.4 Tasks are planned and sequenced in conjunction with others involved in or affected by the work.
  • 1.5 Tools and equipment, including personal protective equipment, are selected and checked for serviceability.
  • 1.6 Work area is prepared to support efficient flashing of penetrations through roofs and walls.
  • 1.7 Sustainability principles and concepts are applied throughout the installation process.
2 Identify flashing requirements.
  • 2.1 Roof and wall penetrations are identified from plans and specifications.
  • 2.2 Penetrations are assessed to allow for the location of existing and future services.
  • 2.3 Materialrequirements are calculated from the job specification, in compliance with standards.
  • 2.4 Materials are identified, ordered and collected according to workplace procedures.
  • 2.5 Materials and equipment are checked for compliance with docket and order form, and for acceptable condition.
3 Flash penetrations.
  • 3.1 Fabrication is undertaken according to plans and specifications.
  • 3.2 Penetration is positioned and cut in compliance with plans, specifications and site measurements.
  • 3.3 Structural supports are installed according to plans, specifications and the building code.
  • 3.4 Opening is prepared in compliance with plans and specifications, manufacturer recommendations and regulations.
  • 3.5 Proprietary or purpose-made flashing is fitted according to standards, plans, specifications and regulations.
  • 3.6 Where required, sealant is applied in compliance with specifications and manufacturer recommendations.
  • 3.7 Penetration is performance tested to ensure correct fit of completed installation, and remedied as required.
4 Clean up.
  • 4.1 Work area is cleared and materials disposed of, reused or recycled according to legislation, regulation, codes of practice and job specification.
  • 4.2 Tools and equipment are cleaned, checked, maintained and stored according to manufacturer recommendations and workplace procedures.
  • 4.3 Informationis accessed and documentation completed according to workplace requirements.
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Work health and safety is to be according to commonwealth, state and territory legislation and regulations and may include:
handling of materials
hazard control
hazardous materials and substances
protective clothing and equipment prescribed under legislation, regulations and workplace policies and practices
safe operating procedures, including recognising and preventing hazards associated with:
electricity
dangerous materials
service lines
surrounding structures and facilities
trip hazards
use of drilling and cutting tools
work site visitors and the public
working at heights
working in proximity to others
use of firefighting equipment
use of first aid equipment
use of tools and equipment
workplace environment and safety.

Environmental requirements cover water quality management and may include:
clean-up protection
stormwater protection
waste management.

Quality assurance requirements may include:
Australian standards
Environment Protection Authority (EPA)
internal company quality assurance policy and risk management strategy
International Standards Organisation
National Construction Code
site safety plan
workplace operations and procedures.

Tools and equipment may include:
fall protection equipment
hand and power tools
ladders
measuring equipment
lifting and load shifting equipment, including:
chain blocks
cranes
elevated work platforms
forklifts
hand trolleys
hoists
jacks
restricted height scaffolds
rollers.

Sustainability principles and concepts:
cover the current and future social, economic and environmental use of resources
may include:
appropriate material selection to ensure minimal environmental impact
rainwater harvesting
choice of efficient products
efficient use of material
recycling of material.

Materials used for flashing roof penetrations may include approved materials, such as:
fibreglass
laminate
metal roof covers of concealed or pierce fixed types
plastic building sheets for walls and roofs
polyethylene
rainwater goods
thermal insulation of reflective foil
fixings, which may include:
metal self drilling and tapping screws
rivets
sealants (approved silicone and solder)
or other approved materials.

Information may include:
charts and hand drawings
instructions issued by authorised organisational or external personnel
manufacturer specifications and instructions
material safety data sheets (MSDS)
memos
organisation work specifications and requirements
plans and sketches
regulatory and legislative requirements, particularly those pertaining to:
building codes
WHS and environmental requirements
plumbing regulations
relevant Australian standards
safe work procedures relating to the flashing of roof penetrations
signage
verbal, written and graphical instructions
work bulletins
work schedules, plans and specifications.
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed in the workplace or a close simulation of the workplace environment providing that simulated or project-based assessment techniques fully replicate plumbing and services workplace conditions, materials, activities, responsibilities and procedures.

Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person who demonstrates competency in this unit must be able to provide evidence of:
locating, interpreting and applying relevant information, standards and specifications to the flashing of penetrations through roofs and walls
applying safety requirements throughout the work sequence, including the use of personal protective clothing and equipment
given the plans and specifications, set out, cut and flash penetrations through openings within a range of up to 300mm diameter and up to 300mm square, one through a roof and one through a wall, ensuring:
application of sustainability principles and concepts
correct identification of requirements and details of the proposed penetration
correct selection and use of appropriate processes, tools and equipment
completing all work to specification
compliance with regulations, standards and organisational quality procedures and processes
communicating and working effectively and safely with others.

Context of and specific resources for assessment
This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints.
Assessment of essential underpinning knowledge will usually be conducted in an off-site context.
Assessment is to comply with relevant regulatory or Australian standards' requirements.
Resource implications for assessment include:
an induction procedure and requirement
realistic tasks or simulated tasks covering the minimum task requirements
relevant specifications and work instructions
tools and equipment appropriate to applying safe work practices
support materials appropriate to activity
workplace instructions relating to safe work practices and addressing hazards and emergencies
material safety data sheets
research resources, including industry-related systems information.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.

Method of assessment
Assessment methods must:
satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package
include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
reinforce the integration of employability skills with workplace tasks and job roles
confirm that competency is verified and able to be transferred to other circumstances and environments.
Validity and sufficiency of evidence requires that:
competency will need to be demonstrated over a period of time reflecting the scope of the role and the practical requirements of the workplace
where the assessment is part of a structured learning experience the evidence collected must relate to a number of performances assessed at different points in time and separated by further learning and practice, with a decision on competency only taken at the point when the assessor has complete confidence in the person's demonstrated ability and applied knowledge
all assessment that is part of a structured learning experience must include a combination of direct, indirect and supplementary evidence.
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.
Replaces
State Code National Code Title Type
D7417 CPCPCM3011A Flash penetrations through roofs and walls Unit of competency
Replaced By
State Code National Code Title Type
OCO77 CPCPCM3021 Flash penetrations through roofs and walls Unit of competency