Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Install and maintain public lighting systems in a very remote community
Install and maintain public lighting systems in a very remote community
Unit of competency
National Code
UETDRRC003
UETDRRC003
State Code
ODN33
ODN33
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
21/12/2021
Field of Education
031311 - Powerline Installation And Maintenance
Original Release Date
21/12/2021
Nominal Hours
36
Description
This unit involves the skills and knowledge required to install and maintain overhead and underground public lighting systems in very remote communities in the electricity supply industry (ESI).It includes the installation and maintenance of public lighting poles/columns, street lighting cable, hardware and components, wiring and earthing systems. It also includes the inspection, testing and commissioning associated with the public lighting system.All work on public lighting systems within very remote communities must be undertaken in an isolated environment other than for testing purposes. The application of the skills and knowledge described in this unit may require a licence/registration to practice in the workplace.Other conditions may also apply under state and territory legislative and regulatory licensing requirements which must be confirmed prior to commencing this unit.
Notes
Elements and Performance Criteria
1 Prepare to install and maintain public lighting systems
- 1.1 Legislation, regulations, standards, codes of practice and organisational workplace requirements for the work to be performed are referred to and confirmed
- 1.2 Work plan is obtained and confirmed in accordance with workplace requirements
- 1.3 Materials required for work are determined and obtained in accordance with work plan and workplace requirements
- 1.4 Work is prioritised and sequenced for completion in accordance with workplan and workplace requirements
- 1.5 Hazards are identified, risks assessed and control measures identified and applied
- 1.6 Public lighting system is verified as isolated and earthed/short circuited in accordance with workplace requirements
- 1.7 Work permits are received and signed in accordance with workplace requirements
- 1.8 Plant, tools, equipment and personal protective equipment (PPE) required for work are determined, obtained and confirmed in working order
- 1.9 Worksite is prepared in accordance with work plan and workplace requirements
- 1.10 Traffic management plan is confirmed as being in place in accordance with workplace requirements
2 Carry out installation and maintenance of public lighting systems
- 2.1 Legislation, regulations, standards, codes of practice and organisational workplace requirements for the work to be performed are applied and monitored
- 2.2 Lifting, climbing, working at heights and the use of plant, tools, equipment and PPE are carried out in accordance with workplace requirements
- 2.3 Hazard control measures are monitored in accordance with workplace requirements
- 2.4 Excavation/foundation construction is inspected and confirmed as compliant in accordance with work plan and workplace requirements
- 2.5 Public lighting systems are installed and maintained in accordance with work plan and workplace requirements
- 2.6 Hardware, fittings and control gear are installed in accordance with workplace requirements
- 2.7 Street lighting cable and earthing systems are installed in accordance with workplace requirements
- 2.8 Public lighting and hardware are inspected for compliance in accordance with work plan and workplace requirements
- 2.9 Earthing and short circuiting equipment is removed, permit signed off and public lighting system is re-energised in accordance with workplace requirements
- 2.10 Public lighting system is tested and commissioned in accordance with work plan and workplace requirements
- 2.11 Incidents or unplanned events are responded to in accordance with workplace requirements
- 2.12 Quality checks of work are undertaken in accordance with work plan and workplace requirements
3 Complete work and documentation
- 3.1 Completed work is checked for compliance against the work plan and workplace requirements
- 3.2 Incidents or unplanned events are reported in accordance with workplace requirements
- 3.3 Worksite is rehabilitated, cleaned and made safe in accordance with workplace requirements
- 3.4 Plant, tools and equipment are cleaned, checked and returned to storage in accordance with workplace requirements
- 3.5 Surplus materials are returned to storage or disposed of in accordance with workplace requirements
- 3.6 Work records, reports and documentation are completed, and appropriate personnel notified in accordance with workplace requirements
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| OBH74 | UETTDRIS38 | Install and maintain public lighting systems in remote communities | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BHB4 | UET30921 | Certificate III in ESI - Very Remote Community Utilities | Qualification |