Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.

Erect timber structures and features

Erect timber structures and features

Unit of competency
National Code
AHCLSC304
State Code
BAM22
TGA Status
Replaced
DTWD Status
Replaced
Current Release Number
1.00
Current Release Date
27/06/2016
State Implementation and Classification
Approved Date
12/01/2017
Field of Education
040311 - Carpentry And Joinery
Original Release Date
12/01/2017
Nominal Hours
50
Description
This unit of competency describes the skills and knowledge required to erect timber structures and features as a component of landscape project works. This unit applies to individuals who take responsibility for own work and for the quality of the work of others. They use discretion and judgement in the selection, allocation and use of available resources. All work is carried out to comply with workplace procedures.No occupational licensing, legislative or certification requirements are known to apply to this unit at the time of publication.
Notes
Elements and Performance Criteria
1. Plan and prepare work
  • 1.1 Interpret plans and specifications
  • 1.2 Check the quantity and quality of materials to ensure they conform to design drawings and specifications
  • 1.3 Select tools and equipment and check for serviceability
  • 1.4 Identify hazards, assess risks and implement controls accordingly
  • 1.5 Select and use suitable personal protective equipment (PPE)
2. Set out the site and prepare the profile and footings
  • 2.1 Determine and locate services
  • 2.2 Mark out the position of the structure or feature
  • 2.3 Establish profiles to conform to the nominated tolerances
  • 2.4 Excavate and prepare footings according to the type of structure to be erected
3. Prepare and cut timber components
  • 3.1 Prepare components for assembly
  • 3.2 Mark out the length of components and the positions of cuts and joints
  • 3.3 Cut, check and accurately drill components in preparation for joining and assembly
4. Assemble and erect structure
  • 4.1 Fix, join or assemble timber components into position and fix into place
  • 4.2 Install remaining components and fix into position
  • 4.3 Finish off structure to ensure all components are secure and complete
  • 4.4 Apply coatings
5. Check quality of work and clean-up site
  • 5.1 Inspect the quality of finished works to ensure the required standard has been achieved
  • 5.2 Clean debris from structure and site
  • 5.3 Dispose of waste material in an environmentally safe and sensitive manner
  • 5.4 Clean, store and maintain tools and equipment
No information
No information
Replaces
State Code National Code Title Type
D6918 AHCLSC304A Erect timber structures and features Unit of competency
Replaced By
State Code National Code Title Type
ODU93 AHCLSC318 Erect timber structures and features Unit of competency