Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Manage glass processing plant shutdown and restart
Manage glass processing plant shutdown and restart
Unit of competency
National Code
MSFGG4015
MSFGG4015
State Code
OAI95
OAI95
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
22/05/2019
Field of Education
030717 - Plant And Machine Operations
Original Release Date
22/05/2019
Nominal Hours
35
Description
This unit describes the skills and knowledge required to coordinate and document the shutdown and restart of a glass production or processing plant in a safe and efficient manner. The shutdown may be a planned or an unplanned shutdown or emergency situation. This unit typically applies to the leading plant technician on a shift, who uses discretion and judgment to respond to the cause of the shutdown and coordinate all personnel involved in the shutdown to ensure it happens in an orderly a fashion and that the plant is left in the best condition possible for a quick restart. It does not apply to individual plant operators shutting down individual production units. No licensing or certification requirements exist at the time of publication. Relevant legislation, industry standards and codes of practice within Australia must be applied.
Notes
Elements and Performance Criteria
1. Manage shutdown sequence
- 1.1 Check and verify glass plant safety systems and ensure that plant has been made safe
- 1.2 Identify the reason for, or cause of, the plant shutdown by troubleshooting the system using all available data and information systems
- 1.3 Obtain confirmation of the identified shutdown from operators to verify both the nature and the reliability of the shutdown
- 1.4 Initiate procedures to rectify the fault or shutdown cause through repair or readjustment before returning the system to startup status
2. Conduct startup process
- 2.1 Satisfy all start-up permissions prior to startup process being commenced
- 2.2 Safely and efficiently conduct startup and return to normal operation in accordance with workplace procedures
3. Document shutdown and startup process
- 3.1 Accurately complete logs and workplace documentation with required details, actions and responses
- 3.2 Record and report any ongoing production problems to appropriate persons or authority
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| WI510 | MSFGG4007 | Manage glass processing plant shutdown and re-start | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| OEY37 | MSFGG4022 | Manage glass processing plant shutdown and restart | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| BEC6 | MSF40418 | Certificate IV in Glass and Glazing | Qualification |