Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Carry out concreting to simple forms
Carry out concreting to simple forms
Unit of competency
National Code
CPCCCO2013A
CPCCCO2013A
State Code
D7357
D7357
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
15/10/2014
Field of Education
040399 - Building, N.e.c.
Original Release Date
15/10/2014
Nominal Hours
24
Description
This unit of competency specifies the outcomes required to safely install formwork, reinforcement and place and finish concrete for the construction of minor slabs, pathways and other minor works to a specified design finish.The unit includes positioning the truck, placing concrete from truck to work area, spreading concrete and cleaning up site.
Notes
Elements and Performance Criteria
1. Plan and prepare.
- 1.1. Work instructions and operational details are obtained using relevant information, confirmed and applied for planning and preparation purposes.
- 1.2. Safety (OHS) requirements are followed in accordance with safety plans and policies.
- 1.3. Signage and barricade requirements are identified and implemented.
- 1.4. Plant, tools and equipment selected to carry out tasks are consistent with the requirements of the job, checked for serviceability and any faults are rectified or reported prior to commencement.
- 1.5. Materials quantity requirements are calculated in accordance with plans, specifications and quality requirements.
- 1.6. Materials appropriate to the work application are identified, obtained, prepared, safely handled and located ready for use.
- 1.7. Environmental requirements are identified for the project in accordance with environmental plans and regulatory obligations and applied.
2. Erect and strip simple formwork.
- 2.1. Subgrade is prepared.
- 2.2. Formwork design is identified from drawings.
- 2.3. Formwork is erected safely on commencement.
- 2.4. Form release agent is applied to erected formwork where specified.
- 2.5. Timber components are de-nailed following stripping of formwork.
- 2.6. Components are cleaned, stacked and stored for reuse or bundled for removal.
- 2.7. Formwork components are removed from site.
3. Place and tie reinforcement.
- 3.1. Reinforcing components are handled and positioned safely.
- 3.2. Reinforcing bars and mesh are positioned.
- 3.3. Bar chairs and spacers are positioned, with minimum edge cover.
4. Place concrete.
- 4.1. Formwork or excavation is cleaned of excess material and debris prior to concrete placement.
- 4.2. Concrete is safely transported by wheelbarrow.
- 4.3. Pump line/chute is controlled and concrete placed.
- 4.4. Concrete is placed in formwork to specified depth.
- 4.5. Concrete is screeded to the alignment of formwork and project specified datums.
- 4.6. Surface of concrete is finished in accordance with specifications.
5. Clean up.
- 5.1. Work area is cleared and materials disposed of, reused or recycled in accordance with legislation, regulations and codes of practice and job specification.
- 5.2. Plant, tools and equipment are cleaned, checked, maintained and stored in accordance with manufacturer recommendations and standard work practices.
RANGE STATEMENT
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Information includes:
diagrams or sketches
instructions issued by authorised organisational or external personnel
manufacturer specifications and instructions, where specified
MSDS
memos
regulatory and legislative requirements pertaining to concreting
relevant Australian standards
safe work procedures relating to concreting
signage
verbal, written and graphical instructions
work bulletins
work schedules, plans and specifications.
Planning and preparation include:
assessment of conditions and hazards
determination of work requirements and safety plans and policies
equipment defect identification
work site inspection.
Safety (OHS) is to be in accordance with state and territory legislation and regulations and project safety plan and may include:
emergency procedures, including extinguishing fires, organisational first aid requirements and evacuation
handling activities that may require the assistance of others or the use of manual or mechanical lifting devices where size, weight or other issues, such as a disability are a factor
hazard control
hazardous materials and substances
organisational first aid
PPE prescribed under legislation, regulations and workplace policies and practices
safe operating procedures, including the conduct of operational risk assessment and treatments associated with:
earth leakage boxes
lighting
power cables, including overhead service trays, cables and conduits
restricted access barriers
surrounding structures
traffic control
trip hazards
work site visitors and the public
working at heights
working in confined spaces
working in proximity to others
use of firefighting equipment
use of tools and equipment
workplace environmental requirements and safety.
Tools and equipment:
include:
brooms
chutes
edging tools
shovels
trowels
wheelbarrows
may include:
bull floats
hand floats
kibbles
line pumps
stipple devices
trowelling machines.
Quality requirements include:
internal company quality policy and standards
manufacturer specifications where specified
relevant regulations, including Australian standards
workplace operations and procedures.
Materials:
include:
bar chairs
bracing
edge form/boards
fabric sheet mesh
pegs
spacers
may include reinforcing bars.
Environmental requirements include:
clean-up management
dust and noise
stormwater management
vibration
waste management.
Simple formwork includes:
timber or steel edge form to a maximum of 100mm in depth.
Simple reinforcing:
includes:
bar chairs
fabric sheet mesh
spacers
may include:
reinforcing bars
trench mesh.
Simple forms of concrete:
include slabs (not requiring internal beams and piers)
may include:
beam thickeners
channels
garden edges
pathways
post holes
simple concrete aprons.
Concreting includes:
finishing of concrete
floating of the concrete
placing of concrete
screeding, limited to include a hand screed.
Placing of concrete involves movement of concrete from the truck to the work and:
includes:
chutes
wheelbarrows
may include:
kibbles
pump lines.
Finishing of concrete includes:
broomed
hand floating
power floating
sponged
stipple device finish
trowelled
trowelling machine finish
wood floated
other project specified finish.
The range statement relates to the unit of competency as a whole. It allows for different work environments and situations that may affect performance. Bold italicised wording, if used in the performance criteria, is detailed below. Essential operating conditions that may be present with training and assessment (depending on the work situation, needs of the candidate, accessibility of the item, and local industry and regional contexts) may also be included.
Information includes:
diagrams or sketches
instructions issued by authorised organisational or external personnel
manufacturer specifications and instructions, where specified
MSDS
memos
regulatory and legislative requirements pertaining to concreting
relevant Australian standards
safe work procedures relating to concreting
signage
verbal, written and graphical instructions
work bulletins
work schedules, plans and specifications.
Planning and preparation include:
assessment of conditions and hazards
determination of work requirements and safety plans and policies
equipment defect identification
work site inspection.
Safety (OHS) is to be in accordance with state and territory legislation and regulations and project safety plan and may include:
emergency procedures, including extinguishing fires, organisational first aid requirements and evacuation
handling activities that may require the assistance of others or the use of manual or mechanical lifting devices where size, weight or other issues, such as a disability are a factor
hazard control
hazardous materials and substances
organisational first aid
PPE prescribed under legislation, regulations and workplace policies and practices
safe operating procedures, including the conduct of operational risk assessment and treatments associated with:
earth leakage boxes
lighting
power cables, including overhead service trays, cables and conduits
restricted access barriers
surrounding structures
traffic control
trip hazards
work site visitors and the public
working at heights
working in confined spaces
working in proximity to others
use of firefighting equipment
use of tools and equipment
workplace environmental requirements and safety.
Tools and equipment:
include:
brooms
chutes
edging tools
shovels
trowels
wheelbarrows
may include:
bull floats
hand floats
kibbles
line pumps
stipple devices
trowelling machines.
Quality requirements include:
internal company quality policy and standards
manufacturer specifications where specified
relevant regulations, including Australian standards
workplace operations and procedures.
Materials:
include:
bar chairs
bracing
edge form/boards
fabric sheet mesh
pegs
spacers
may include reinforcing bars.
Environmental requirements include:
clean-up management
dust and noise
stormwater management
vibration
waste management.
Simple formwork includes:
timber or steel edge form to a maximum of 100mm in depth.
Simple reinforcing:
includes:
bar chairs
fabric sheet mesh
spacers
may include:
reinforcing bars
trench mesh.
Simple forms of concrete:
include slabs (not requiring internal beams and piers)
may include:
beam thickeners
channels
garden edges
pathways
post holes
simple concrete aprons.
Concreting includes:
finishing of concrete
floating of the concrete
placing of concrete
screeding, limited to include a hand screed.
Placing of concrete involves movement of concrete from the truck to the work and:
includes:
chutes
wheelbarrows
may include:
kibbles
pump lines.
Finishing of concrete includes:
broomed
hand floating
power floating
sponged
stipple device finish
trowelled
trowelling machine finish
wood floated
other project specified finish.
EVIDENCE GUIDE
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person who demonstrates competency in this unit must be able to provide evidence of the ability to:
locate, interpret and apply relevant information, standards and specifications
comply with site safety plan and OHS legislation, regulations and codes of practice applicable to workplace operations
comply with organisational policies and procedures including quality requirements
safely and effectively operate and use tools, plant and equipment
communicate and work effectively and safely with others
prepare subgrade; erect formwork; cut, place and tie reinforcement; place and hand screed concrete for a slab of (4 square metres is recommended) and a minimum depth of 100mm to the required finished level and job specification.
Context of and specific resources for assessment
This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints.
Assessment of essential underpinning knowledge will usually be conducted in an off-site context.
Assessment is to comply with relevant regulatory or Australian standards' requirements.
Resource implications for assessment include:
an induction procedure and requirement
realistic tasks or simulated tasks covering the mandatory task requirements
relevant specifications and work instructions
tools and equipment appropriate to applying safe work practices
support materials appropriate to activity
workplace instructions relating to safe work practices and addressing hazards and emergencies
material safety data sheets
research resources, including industry related systems information.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Method of assessment
Assessment methods must:
satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package
include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
reinforce the integration of employability skills with workplace tasks and job roles
confirm that competency is verified and able to be transferred to other circumstances and environments.
Validity and sufficiency of evidence requires that:
competency will need to be demonstrated over a period of time reflecting the scope of the role and the practical requirements of the workplace
where the assessment is part of a structured learning experience the evidence collected must relate to a number of performances assessed at different points in time and separated by further learning and practice, with a decision on competency only taken at the point when the assessor has complete confidence in the person's demonstrated ability and applied knowledge
all assessment that is part of a structured learning experience must include a combination of direct, indirect and supplementary evidence.
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.
The evidence guide provides advice on assessment and must be read in conjunction with the performance criteria, required skills and knowledge, range statement and the Assessment Guidelines for the Training Package.
Overview of assessment
This unit of competency could be assessed in the workplace or a close simulation of the workplace environment, provided that simulated or project-based assessment techniques fully replicate construction workplace conditions, materials, activities, responsibilities and procedures.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
A person who demonstrates competency in this unit must be able to provide evidence of the ability to:
locate, interpret and apply relevant information, standards and specifications
comply with site safety plan and OHS legislation, regulations and codes of practice applicable to workplace operations
comply with organisational policies and procedures including quality requirements
safely and effectively operate and use tools, plant and equipment
communicate and work effectively and safely with others
prepare subgrade; erect formwork; cut, place and tie reinforcement; place and hand screed concrete for a slab of (4 square metres is recommended) and a minimum depth of 100mm to the required finished level and job specification.
Context of and specific resources for assessment
This competency is to be assessed using standard and authorised work practices, safety requirements and environmental constraints.
Assessment of essential underpinning knowledge will usually be conducted in an off-site context.
Assessment is to comply with relevant regulatory or Australian standards' requirements.
Resource implications for assessment include:
an induction procedure and requirement
realistic tasks or simulated tasks covering the mandatory task requirements
relevant specifications and work instructions
tools and equipment appropriate to applying safe work practices
support materials appropriate to activity
workplace instructions relating to safe work practices and addressing hazards and emergencies
material safety data sheets
research resources, including industry related systems information.
Reasonable adjustments for people with disabilities must be made to assessment processes where required. This could include access to modified equipment and other physical resources, and the provision of appropriate assessment support.
Method of assessment
Assessment methods must:
satisfy the endorsed Assessment Guidelines of the Construction, Plumbing and Services Training Package
include direct observation of tasks in real or simulated work conditions, with questioning to confirm the ability to consistently identify and correctly interpret the essential underpinning knowledge required for practical application
reinforce the integration of employability skills with workplace tasks and job roles
confirm that competency is verified and able to be transferred to other circumstances and environments.
Validity and sufficiency of evidence requires that:
competency will need to be demonstrated over a period of time reflecting the scope of the role and the practical requirements of the workplace
where the assessment is part of a structured learning experience the evidence collected must relate to a number of performances assessed at different points in time and separated by further learning and practice, with a decision on competency only taken at the point when the assessor has complete confidence in the person's demonstrated ability and applied knowledge
all assessment that is part of a structured learning experience must include a combination of direct, indirect and supplementary evidence.
Assessment processes and techniques should as far as is practical take into account the language, literacy and numeracy capacity of the candidate in relation to the competency being assessed.
Supplementary evidence of competency may be obtained from relevant authenticated documentation from third parties, such as existing supervisors, team leaders or specialist training staff.
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| W9384 | CPCCCO2003A | Carry out concreting to simple forms | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| OCQ96 | CPCCCO2013 | Carry out concreting to simple forms | Unit of competency |