Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Licence to perform rigging advanced level
Licence to perform rigging advanced level
Unit of competency
National Code
CPCCLRG4001
CPCCLRG4001
State Code
OCQ70
OCQ70
TGA Status
Current
Current
DTWD Status
Approved
Approved
State Implementation and Classification
Approved Date
01/06/2021
Field of Education
040329 - Scaffolding And Rigging
Original Release Date
01/06/2021
Nominal Hours
24
Description
This unit specifies the skills and knowledge required to safely perform advanced rigging work.Riggers use mechanical load shifting equipment and associated gear to move, place or secure loads, including plant, equipment or members of a building or structure. Riggers ensure the stability of those members and set up and dismantle cranes and hoists. This unit applies to rigging work involving:gin poles and shear legsflying foxes and cable waysguyed derricks and structuressuspended scaffolds and fabricated hung scaffolds.Rigging work is undertaken in construction and other industries where load shifting equipment is used to move, place or secure loads. Completion of the general construction induction training program, specified in the Safe Work Australia model Code of Practice: Construction Work, is required by anyone carrying out construction work. Achievement of CPCWHS1001Prepare to work safely in the construction industry meets this requirement.This unit has a pre-requisite requirement. This requirement may be met by either the successful completion of the unitCPCCLRG3002 Licence to perform rigging intermediate levelor holding a valid licence for intermediate rigging.Competence in this unit does not in itself result in a licence. A licence is obtained after competence is assessed under applicable Commonwealth, state or territory work health and safety (WHS) regulations.
Notes
Elements and Performance Criteria
1 Plan task.
- 1.1 Review task instructions, consult with relevant persons to seek clarification as required, and obtain relevant workplace information.
- 1.2 Obtain and interpret information, including safe work method statements (SWMSs), required to ensure that activities are performed in compliance with workplace-specific and safe work requirements.
- 1.3 Obtain and interpret information required to ensure that equipment inspection, use, maintenance and storage complies with manufacturer requirements.
- 1.4 Identify workplace and task-specific hazards and determine required risk controls and safety measures and equipment, including signs and barricades, personal protective equipment (PPE), and fall prevention and fall arrest equipment.
- 1.5 Identify methods of moving and placing tools, equipment and materials to minimise the risk of falling objects, to avoid inappropriate carrying on ladders and to minimise hazardous manual tasks.
- 1.6 Identify required rigging equipment and associated gear.
- 1.7 Calculate loads associated with mechanical load shifting equipment and associated gear required to erect and dismantle structures and plant.
- 1.8 Establish communication methods with associated personnel.
2 Select and inspect equipment.
- 2.1 Select risk controls and equipment, including fall prevention and fall arrest equipment, and check that it is working and fit for purpose.
- 2.2 Select and check PPE.
- 2.3 Select rigging equipment and associated gear, inspect for defects, and isolate, tag out, report and record defective items.
- 2.4 Select communication equipment and check that it is working and fit for use.
3 Set up task.
- 3.1 Establish and maintain communication with relevant persons to ensure task plan and risk controls are communicated clearly, including any impact on other workplace activities.
- 3.2 Ensure risk controls and safety measures and equipment have been put in place, including the fitting, adjusting and anchoring of fall protection equipment.
- 3.3 Consult with relevant persons to ensure that ground and foundation have been assessed as suitable for task.
- 3.4 Consult with relevant persons to ensure that the structure has been assessed as suitable for load bearing task.
4 Undertake advanced rigging activities.
- 4.1 Erect, operate and dismantle all structures and plant while maintaining stability, in accordance with workplace and manufacturer requirements.
- 4.2 Erect gin poles or sheer legs, operate winch to move load, and dismantle.
- 4.3 Erect flying fox or cable way, operate to move a load, and dismantle.
- 4.4 Erect guyed derrick, operate to move a load, and dismantle.
- 4.5 Erect, operate and dismantle suspended scaffold.
- 4.6 Install and remove fabricated hung scaffold.
5 Complete task.
- 5.1 Remove excess materials from work area.
- 5.2 Inspect structures, plant, equipment and gear for defects, and isolate, tag out and report defective items.
- 5.3 Store plant, equipment and gear in accordance with workplace requirements.
- 5.4 Remove risk controls safety measures and equipment.
- 5.5 Complete handover certificates, and attach scaffolding tags for suspended scaffold and hung scaffold.
No information
No information
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| W9428 | CPCCLRG4001A | Licence to perform rigging advanced level | Unit of competency |