Whilst all efforts are made to provide accurate and timely information from the relevant source/documentation, please be aware that the information supplied may not be the most current version. The accuracy of the detail has not been confirmed by the Department and therefore should not be relied upon without first confirming the contents.
Apply time management techniques
Apply time management techniques
Unit of competency
National Code
BSBPMG402A
BSBPMG402A
State Code
D0922
D0922
TGA Status
Replaced
Replaced
DTWD Status
Replaced
Replaced
State Implementation and Classification
Approved Date
20/06/2013
Field of Education
080315 - Project Management
Original Release Date
20/06/2013
Nominal Hours
40
Description
This unit describes the performance outcomes, skills and knowledge required to assist with project scheduling activities, the application and monitoring of the agreed schedule and evaluation of time management effectiveness for the project.No licensing, legislative, regulatory or certification requirements apply to this unit at the time of endorsement.
Notes
Elements and Performance Criteria
1. Assist in the development of project schedules
- 1.1. Contribute, within delegated authority, to determining the duration and effort, sequence and dependencies of tasks to meet project objectives
- 1.2. Use project scheduling tools and techniques to help establish and integrate planned time management aspects of the schedule, resource allocation and financial requirements
- 1.3. Contribute to the agreement process and communication of the schedule to the client and other stakeholders
2. Apply agreed schedules
- 2.1. Use techniques to measure, record and report progress of activities in relation to agreed schedules and plans
- 2.2. Record variance between actual and planned progress and report to others for remedial action
- 2.3. Contribute to forecasting the impact of changes on the schedule and to the analysis of options
- 2.4. Implement agreed changes to the schedule and update plans as directed to accommodate changing situations throughout the project
3. Participate in assessing time management outcomes
- 3.1. Provide assistance in the review of project outcomes to determine the effectiveness of time management tools, techniques and approaches used
- 3.2. Report scheduling and time management issues and responses to project manager for application in future projects
in a multi-disciplinary environment subject to frequent change
under limited guidance and supervision
within agreed authorisation and limits
within established organisational framework, procedures and routines
assisting in qualitative and/or quantitative time analysis, such as schedule simulation, work breakdown structure, decision analysis, contingency planning and alternative strategy development
using personal experience and/or experts
using specialist time analysis tools to provide output to assist in the decision making process
diaries, incident logs, occurrence reports and other similar documentation
lists of potential schedule events
project and/or organisation files and records
relevant authority
project manager
project specialists or other personnel
team members
achievement of agreed major milestones, for example phases and sub-contracts
change of key personnel
delivery of major deliverables
finalisation of project and other agreed milestones
under limited guidance and supervision
within agreed authorisation and limits
within established organisational framework, procedures and routines
assisting in qualitative and/or quantitative time analysis, such as schedule simulation, work breakdown structure, decision analysis, contingency planning and alternative strategy development
using personal experience and/or experts
using specialist time analysis tools to provide output to assist in the decision making process
diaries, incident logs, occurrence reports and other similar documentation
lists of potential schedule events
project and/or organisation files and records
relevant authority
project manager
project specialists or other personnel
team members
achievement of agreed major milestones, for example phases and sub-contracts
change of key personnel
delivery of major deliverables
finalisation of project and other agreed milestones
Overview of assessment
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the following is essential:
application of time management techniques in relation to multiple complex projects
knowledge of tools and techniques for monitoring project schedules.
Context of and specific resources for assessment
Assessment must ensure:
access to workplace documentation such as diaries, progress reports, spreadsheets, and other planning tools with timeframes linked to outcomes.
Method of assessment
A range of assessment methods should be used to assess practical skills and knowledge. The following examples are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third party workplace reports of on-the-job project time management performance by the candidate
analysis of responses to case studies and scenarios addressing project time management issues and problems
oral or written questioning to assess knowledge of strategies, tools and techniques for managing project time and their particular application/s
review of techniques used to measure, record and report progress of activities in relation to agreed schedules and plans
assessment of changes implemented to the schedule and the updating of plans to accommodate changing situations throughout the project.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended, for example:
other units from the Certificate IV in Project Management.
Critical aspects for assessment and evidence required to demonstrate competency in this unit
Evidence of the following is essential:
application of time management techniques in relation to multiple complex projects
knowledge of tools and techniques for monitoring project schedules.
Context of and specific resources for assessment
Assessment must ensure:
access to workplace documentation such as diaries, progress reports, spreadsheets, and other planning tools with timeframes linked to outcomes.
Method of assessment
A range of assessment methods should be used to assess practical skills and knowledge. The following examples are appropriate for this unit:
direct questioning combined with review of portfolios of evidence and third party workplace reports of on-the-job project time management performance by the candidate
analysis of responses to case studies and scenarios addressing project time management issues and problems
oral or written questioning to assess knowledge of strategies, tools and techniques for managing project time and their particular application/s
review of techniques used to measure, record and report progress of activities in relation to agreed schedules and plans
assessment of changes implemented to the schedule and the updating of plans to accommodate changing situations throughout the project.
Guidance information for assessment
Holistic assessment with other units relevant to the industry sector, workplace and job role is recommended, for example:
other units from the Certificate IV in Project Management.
Replaces
| State Code | National Code | Title | Type |
|---|---|---|---|
| C7051 | BSBPM402A | Apply time management techniques | Unit of competency |
Replaced By
| State Code | National Code | Title | Type |
|---|---|---|---|
| WG089 | BSBPMG410A | Apply project time-management techniques | Unit of competency |
| State Code | National Code | Title | Type |
|---|---|---|---|
| J283 | PSP40112 | Certificate IV in Government | Qualification |
| J290 | PSP41212 | Certificate IV in Government (Project Management) | Qualification |
| 7162 | 52180 | Certificate IV in Leadership Development | Accredited course |
| 7184 | 52559WA | Certificate IV in Leadership Development | Accredited course |
| D359 | CUS40309 | Certificate IV in Music Business | Qualification |
| D158 | BSB41507 | Certificate IV in Project Management | Qualification |
| S672 | FPI40310 | Certificate IV in Timber Truss and Frame Manufacture | Qualification |